Summary
- Applied Digital has signed an 18-year lease with an unnamed investment-grade hyperscale customer, incorporating higher pricing than previous agreements.
- Initial capacity deliveries are anticipated during the first half of 2028, subject to development, utility, and regulatory requirements.
- Applied Digital has already provided initial equity funding and intends to arrange further project financing against the lease.
American data centre developer Applied Digital has signed an 18-year lease covering 150MW of critical IT capacity, with the agreement expected to generate approximately $5.4bn in contracted revenue over its initial term.
The customer, described by Applied Digital as an investment-grade hyperscaler, has not been identified. The developer anticipates beginning capacity deliveries during the first half of 2028, subject to development milestones, utility arrangements, and regulatory approvals.
Renewal options could extend the agreement to 33 years and increase its potential value to approximately $12.7bn. Those additional revenues remain dependent on the customer exercising its contractual options.
Applied Digital says the agreement incorporates improved commercial terms, including higher pricing than its previous leases. The company has not disclosed the detailed pricing structure or the allocation of responsibilities for future equipment and infrastructure upgrades.
The transaction increases Applied Digital’s portfolio-wide contracted base-term lease revenue beyond $41bn. Exercising all renewal options across its existing agreements could increase that figure to approximately $100bn, although those optional extensions do not represent committed revenue.
The duration and value of the agreements reflect the capital expenditure associated with large computing campuses, where developers must finance substantial electrical, mechanical, and structural infrastructure before customers can occupy their facilities.
Institutional capital supports construction
Applied Digital has already provided initial equity funding for the development through its own resources and its $5bn investment partnership with Macquarie Asset Management. It intends to arrange additional project financing supported by the new lease.
Separating initial equity expenditure from subsequent borrowing allows developers to finance preparatory activities before establishing the longer-term funding required to complete construction.
Land acquisition, engineering design, preparatory construction, and advance equipment procurement can require considerable expenditure before a facility reaches the milestones against which lenders are prepared to release construction finance.
A committed customer provides lenders with a basis for assessing the revenues expected from a completed facility. The customer’s creditworthiness, contractual obligations, and the conditions attached to capacity delivery can influence the financing terms available to the developer.
Approximately 75% of Applied Digital’s contracted base-term lease revenue is now attributable to investment-grade customers. Its portfolio encompasses more than 1.6GW of contracted critical IT load and 2.2GW of grid-connected peak load.
The two capacity measures describe different aspects of the portfolio. Critical IT load refers to the electricity requirements of computing equipment, whereas peak electrical demand encompasses the supporting infrastructure necessary to operate those systems. Neither figure establishes how much computing capacity is currently operational.
Applied Digital expects to complete outstanding project financing for Delta Forge 1 and Polaris Forge 3 during the first quarter of 2027, followed by Delta Forge 2 during the second quarter.
The sequencing allows financing commitments to follow the progress of individual developments, rather than requiring the entirety of the company’s capital programme to be funded simultaneously.
Long-term contracts underpin infrastructure investment
European data centre developers face comparable financing requirements when pursuing hyperscale construction programmes. The availability of powered development land, suitable electricity procurement arrangements, and credible customer commitments can determine whether individual projects attract sufficient capital.
Establishing a lease before construction reduces uncertainty concerning future occupancy, but it does not remove the risks associated with delivering the infrastructure.
Delays in obtaining electricity connections or installing major electrical equipment can postpone the availability of contracted capacity. Developers must continue financing construction activity during those delays, potentially extending the period before rental revenues become available.
Long contractual periods also introduce considerations extending beyond initial construction. Data centre buildings and their mechanical and electrical systems may remain in service across several generations of computing hardware, with customer requirements changing as equipment power densities increase.
The allocation of responsibility for maintaining, replacing, and adapting infrastructure can consequently influence the long-term economics of individual leases.
Institutional investors assessing such developments must distinguish between anticipated contractual revenues and the cash flows remaining after construction expenditure, operating costs, financing obligations, and subsequent infrastructure investment.
The higher pricing achieved under Applied Digital’s latest agreement could improve its commercial position, although the absence of detailed pricing and development expenditure figures prevents an independent assessment of the project’s expected returns.
The agreement provides a substantial additional customer commitment and a basis for arranging further project finance. Delivering its associated revenues will depend on Applied Digital completing the electrical connections, construction work, and commissioning activities required to make the contracted capacity available from 2028.