Daikin develops 60MW AI cooling architecture

Daikin develops 60MW AI cooling architecture

Daikin Applied has developed a cooling architecture for AI infrastructure. Its D60-W reference design supports 60MW of IT load, combining liquid cooling, water-cooled chillers, dry coolers, and integrated controls across…

Daikin develops 60MW AI cooling architecture
Summary
  • Daikin's D60-W reference architecture supports 60MW of IT load, with 92% of computing heat removed through liquid cooling and 8% through air cooling.
  • The design incorporates water-cooled chillers, dry coolers, and a facility water supply temperature of 22°C.
  • Its modular configuration supports phased infrastructure deployment, although some equipment has a later commercial availability date.

Daikin Applied has developed a cooling reference architecture for AI computing facilities with 60MW of IT load, combining mechanical refrigeration, liquid cooling, and dry heat rejection equipment within a design based on Nvidia’s DSX AI Factory Platform and Vera Rubin NVL72 computing systems.

The D60-W architecture, introduced on 10 November, divides the computing installation into six deployable units. Approximately 92% of the IT load’s heat is assigned to liquid cooling, with the remaining 8% accommodated through air cooling infrastructure.

At the reference design’s full computing load, those proportions correspond to approximately 55.2MW and 4.8MW of heat respectively. Additional thermal loads associated with electrical losses, mechanical equipment, and other facility services must also be considered when sizing the complete installation.

Daikin’s configuration incorporates water-cooled chillers, dry coolers, heat exchangers, pumps, and integrated controls, maintaining a specified facility water supply temperature of 22°C.

The architecture establishes a design framework for developers and engineering contractors rather than representing a completed facility. Some of the specified equipment is scheduled for commercial availability during the second half of 2027.

Cooling circuits connect computing equipment and mechanical plant

Direct-to-chip cooling transfers heat from processors into liquid circulating through cold plates attached to computing components. Coolant distribution units provide an interface between those circuits and the facility’s wider mechanical infrastructure, allowing the two systems to operate under different fluid quality, temperature, and pressure requirements.

The heat removed through that process must subsequently be transferred into the external environment or recovered for another application.

Daikin’s architecture uses dry coolers instead of conventional evaporative cooling towers for external heat rejection. Air passing across the dry cooler’s heat exchanger removes energy from circulating fluid without the routine evaporative water consumption associated with wet cooling towers.

The achievable cooling performance depends on outdoor temperatures and the difference between those temperatures and the circulating fluid. During sufficiently cool conditions, dry cooling equipment can remove heat with little or no mechanical refrigeration.

As outdoor temperatures rise, the available temperature difference decreases. Water-cooled chillers can then provide additional refrigeration to maintain the required facility water temperature.

Intermediate operating conditions may support hybrid operation, with dry coolers removing part of the thermal load before mechanical refrigeration completes the process.

Maintaining the specified water supply temperature requires controls that coordinate these operating modes while accounting for equipment availability, computing demand, and the electrical consumption of the cooling plant.

The configuration’s 22°C water temperature is therefore an important design parameter. Increasing the temperature at which heat can be transferred away from computing equipment can extend opportunities for economiser operation, but the permitted temperature range remains dependent on the requirements of the connected hardware.

Mechanical infrastructure must accommodate phased construction

Dividing the 60MW installation into six deployable units gives developers a framework for coordinating cooling investment with the delivery of computing capacity.

Large data centre campuses frequently enter operation in phases, particularly where electricity connections, equipment availability, or customer delivery requirements prevent all computing infrastructure from being commissioned simultaneously.

Installing mechanical capacity in stages can reduce the amount of equipment purchased before it is needed. However, shared pipework, electrical infrastructure, controls, and external heat rejection systems must be designed to accommodate subsequent expansion without compromising operational facilities.

Redundancy must similarly extend across the mechanical installation. Spare refrigeration capacity provides limited protection if failures within shared pumping equipment, electrical supplies, or control systems prevent coolant from reaching the computing equipment.

For developments in Europe, local climatic conditions will influence the suitability of Daikin’s proposed heat rejection strategy. Facilities in northern Europe may have greater opportunities to exploit outdoor cooling conditions than installations operating in warmer Mediterranean environments.

Dry heat rejection can reduce operational water demand, but its electrical consumption and equipment footprint must be assessed against the temperatures experienced throughout the year. The appropriate configuration will depend on the relationship between water availability, electricity costs, available land, and the operating requirements of the computing installation.

The reference architecture provides a starting point for those engineering decisions while establishing a defined relationship between rack-level cooling and the facility’s mechanical plant.

Detailed design, equipment procurement, system integration, and commissioning remain necessary before individual developments can establish their actual cooling capacity, resilience, and energy performance.