Summary
- Germany has 20 projects under construction, followed by Spain with 17, France with nine, and Switzerland with eight.
- The UK has 35 developments permitted or with contractors appointed but only six under construction.
- Reported facility power, IT load, and grid connection ratings cannot be combined into a single reliable capacity figure.
Germany and Spain account for almost a third of European data centre projects under construction, according to infrastructure intelligence provider DC Blueprint, which has identified 118 active construction projects across 22 countries.
The company’s assessment, dated 25 November, covers 585 developments, with another 107 having obtained permission or appointed a contractor without beginning construction. Approximately one-fifth of the overall inventory has entered the construction stage.
Germany leads with 20 projects under construction from an identified pipeline of 67, followed by Spain with 17 of 56. France has nine of its 53 tracked developments under construction, while Switzerland has eight from a substantially smaller inventory of 12.
Together, those four countries account for 54 active construction projects, equivalent to around 46% of the European total identified by the research. Finland and the Netherlands each have seven projects under construction, followed by the UK and Türkiye with six apiece.
Switzerland has the highest proportion of tracked developments under construction, at approximately 67%. By comparison, construction has yet to commence on any of the 25 Polish projects identified within the dataset.
The figures describe project numbers rather than the distribution of additional computing capacity. A relatively small regional facility and a hyperscale campus containing several buildings can each represent a single entry while requiring substantially different volumes of investment and electricity infrastructure.
UK permitted pipeline exceeds construction activity
The UK has the largest inventory of developments awaiting construction among the markets examined. DC Blueprint identifies 35 projects holding permission or having appointed contractors, compared with six under construction from a total of 92 tracked developments.
That represents almost six developments awaiting construction for every project where work has commenced. Germany has 13 projects within the equivalent pre-construction classification, while Spain has five.
The difference does not establish the cause of individual project delays. Developments may remain between permission and construction while developers establish financing arrangements, secure customers, complete detailed designs, or coordinate equipment procurement with electricity infrastructure programmes.
However, electricity connection availability remains an important consideration within the UK development market. The progression of large computing facilities can depend on separate construction programmes covering substations, transmission connections, and other network assets outside their development boundaries.
Beginning construction before those arrangements are sufficiently established can expose developers to substantial financial risk. Capital committed to buildings and equipment may remain unproductive if electricity infrastructure cannot be completed within the anticipated operating timetable.
Ireland also has more projects awaiting construction than undergoing building work, with nine developments in the permitted or contractor-appointed classification against five under construction. Italy has five active construction projects from a wider inventory of 54, with much of its development activity remaining at earlier stages.
Construction activity and measurable capacity
DC Blueprint classifies projects as under construction once preparatory works or physical building activity have commenced, based on publicly available evidence. Nine additional developments where the building structure has been completed are counted separately.
Including preparatory works means the classification encompasses projects at different stages of physical development. A site undergoing initial excavation may still require substantial construction and engineering work before it can accommodate computing equipment.
Even after a building’s structure is complete, electrical distribution, mechanical cooling, controls, security infrastructure, and communications systems must be installed and commissioned before the facility can enter service.
The research also highlights inconsistencies in how proposed capacity is disclosed. Only 18 of the 118 active construction projects identify a facility power rating, collectively representing approximately 2,648MW at full development. Other projects provide IT load figures, electricity connection ratings, or no comparable capacity information.
Those different measurements are not interchangeable. IT load describes the power available to computing equipment, whereas facility demand includes supporting infrastructure such as cooling and electrical distribution. A grid connection rating may also incorporate capacity reserved for subsequent expansion.
As DataCentral reported earlier this month, an earlier European infrastructure inventory identified 482 developments. The increase in tracked projects should not be interpreted directly as market growth because changes in research coverage can also affect the number of developments recorded.
The November construction assessment provides a more specific measure of physical development activity across European markets. Germany and Spain currently lead by project count, but establishing their eventual contribution to European computing capacity will require further evidence concerning project size, commissioning schedules, and electricity availability.