Summary
- Gartner forecasts European data centre systems expenditure of $167.7bn in 2027, compared with $129.2bn in 2026.
- European spending on AI-optimised servers is expected to reach $79.7bn.
- Hardware inflation and electricity availability complicate the relationship between expenditure and additional operational computing capacity.
European expenditure on data centre systems is forecast to increase by 29.7% to $167.7bn in 2027, according to new research from Gartner, as rising equipment prices combine with demand for additional high-performance computing capacity.
The forecast, published on 24 November, follows estimated expenditure of $129.2bn in 2026, representing annual growth of 54.1%.
Gartner expects data centre systems to remain the fastest-growing major category of European information technology expenditure during 2027. Spending on AI-optimised servers alone is forecast to reach $79.7bn.
The research company expects server prices to reach three times their 2024 levels, reflecting substantial changes in the cost of computing equipment over a relatively short period.
Total European IT expenditure is forecast to increase by 9.9% to $1.57tn, with infrastructure-as-a-service spending rising separately from approximately $64.9bn to $82.3bn.
Gartner bases its forecasts on analysis of technology sales across more than 1,000 suppliers. Its data centre systems category concerns computing infrastructure products rather than the total capital expenditure associated with constructing and operating data centre buildings.
Hardware expenditure rises faster than equipment volumes
Increasing server prices complicate comparisons between capital expenditure and the amount of additional computing capacity acquired through that investment.
Advanced computing systems incorporate processors, memory, storage, networking components, and electrical conversion equipment sourced through interconnected manufacturing supply chains.
Shortages affecting individual components can increase the price of complete systems, including those whose technical specifications have remained substantially unchanged.
Earlier November research from IDC identified worldwide AI infrastructure spending of $121.4bn during the second quarter of 2026, with Western Europe recording expenditure of approximately $6.4bn.
IDC identified memory pricing as an increasingly important contributor to market growth. Hyperscale operators have secured substantial quantities of available supply through long-term agreements, while other equipment purchasers remain exposed to prevailing component prices.
The research company expects elevated pricing to continue through at least the second half of 2027.
Demand is also extending beyond accelerator-based hardware. IDC’s worldwide figures showed expenditure on non-accelerated AI infrastructure increasing by approximately 61% compared with the corresponding quarter of 2025, against growth of approximately 52% for accelerated systems.
Those systems support activities including data preparation and coordination of AI workloads, which can require different computing platforms from those used to train and operate large models.
Facilities accommodating a broader range of hardware must therefore establish how different computing densities and equipment configurations can be supported through their existing electrical and mechanical infrastructure.
Physical infrastructure constrains hardware deployment
Higher expenditure on computing equipment will not translate immediately into additional operational capacity where data centre construction and electricity connections remain outstanding.
Infrastructure developers frequently need to commit substantial expenditure to electrical distribution equipment, cooling systems, and buildings before the customer hardware can be installed.
Increases in the cost of computing equipment between those investment decisions and the eventual installation date can alter the overall commercial requirements of a development.
Customers may revise their procurement programmes, introduce hardware in smaller phases, or reassess equipment configurations in response to changes in purchasing costs.
Changes to the specified computing platforms can also affect the engineering assumptions used to design individual data halls, including power density, coolant flow requirements, and network architecture.
DataCentral has previously examined how rising AI server prices could affect infrastructure budgets as component availability influences the commercial terms under which computing equipment is purchased.
Electricity availability introduces a separate constraint. Even where computing hardware has been acquired and buildings are complete, facilities cannot deliver their intended capacity until the necessary power distribution and cooling infrastructure is operational.
Coordinating equipment procurement with the delivery of electricity infrastructure will remain important as both hardware expenditure and the physical scale of European data centre developments increase.
Gartner’s forecast indicates that the equipment supporting Europe’s computing infrastructure will absorb substantially more investment in 2027. The resulting expansion in commercially available capacity will depend on the volume and performance of the hardware acquired, alongside the rate at which facilities can accommodate it.