Nordic consortium proposes distributed AI gigafactory network

Nordic consortium proposes distributed AI gigafactory network

Nokia, Nscale, Skeleton, Telia, and Verda have formed AI Gigafactory Northern, proposing a distributed computing infrastructure network across Finland, Estonia, Latvia, and Sweden under the European EuroHPC programme.

Nordic consortium proposes distributed AI gigafactory network
Summary
  • Five technology and infrastructure companies have established AI Gigafactory Northern to pursue a federated, multi-site computing development.
  • The proposal identifies Oulu, Iru, and Valmiera as prospective locations, with a fourth site in Sweden still to be selected.
  • The consortium intends to bid under EuroHPC's AI Gigafactory procurement process but has not secured an award, confirmed its capacity, or committed to construction.

Nokia, Nscale, Skeleton Technologies, Telia, and Verda have formed a consortium proposing a distributed AI computing infrastructure network across Finland, Estonia, Latvia, and Sweden.

The group, named AI Gigafactory Northern, intends to bid under the European High-Performance Computing Joint Undertaking’s procurement programme for new large-scale AI computing facilities.

Its proposed network would connect facilities in Oulu, Finland; Iru, near Tallinn in Estonia; and Valmiera, Latvia. A fourth location is envisaged in Sweden, although the partners have not selected the site.

The consortium intends to operate the facilities through a federated model, combining computing infrastructure, cloud services, high-capacity telecommunications networks, and supporting electrical systems across several countries.

Formation of the consortium establishes a partnership and proposed development model rather than an approved construction programme.

The companies have not disclosed a total project investment, aggregate IT capacity, electricity connection requirement, construction timetable, or completed funding arrangement for the proposed network.

Nor has EuroHPC announced that the consortium has been selected to receive a contract under the programme.

Computing would be distributed across four countries

The proposed arrangement differs from a conventional data centre campus in which most computing equipment is concentrated at one location.

AI Gigafactory Northern intends to connect infrastructure across several sites, allowing computing services to be coordinated through a shared operational and commercial model.

The arrangement would require reliable telecommunications connectivity between the participating facilities, alongside local electrical, cooling, and building infrastructure at each location.

Nokia is contributing networking and connectivity expertise, including the systems required to connect computing infrastructure across different sites.

Nscale brings experience in developing and operating AI computing environments and cloud platforms. Verda contributes AI infrastructure and cloud services capabilities intended to support training and inference workloads.

Telia, alongside its subsidiary Telia Cygate, will contribute telecommunications, systems integration, and infrastructure operations expertise.

Skeleton Technologies is participating through its electrical power systems business, with the consortium identifying power management and the ability to accommodate changing computing demand among its technical priorities.

Large AI computing systems can create substantial variations in electricity consumption as processor workloads change. Managing those variations may require coordination between computing equipment, electrical distribution systems, and the available electricity supply.

Power conditioning and energy storage technologies can be used to manage certain changes in electrical demand, although the equipment and control arrangements needed depend on the final facility design.

The consortium has not identified a complete electrical architecture for any of its proposed locations or confirmed the power systems that will be installed.

A distributed computing arrangement also creates requirements for data transfer between sites. The feasibility of dividing workloads across multiple facilities depends on network bandwidth, latency, data location requirements, and the software used to coordinate computing resources.

Some activities can be distributed between geographically separated locations more readily than others. Computing processes that require frequent exchanges of large amounts of data may be more sensitive to network latency and capacity.

The proposed federation could allow some services to be provided from different locations, but the consortium has not disclosed a workload scheduling architecture or the extent to which computing jobs would operate across sites simultaneously.

Geographical separation can also support resilience by reducing dependence on one physical facility. That benefit depends on the actual redundancy, connectivity, storage, and recovery arrangements implemented in the completed system.

The consortium’s stated distributed architecture should therefore not be treated as evidence that a particular level of service availability has already been achieved.

Electricity availability will influence site development

Northern Europe offers a combination of relatively cool climatic conditions, established telecommunications infrastructure, and access to electricity from lower-carbon generation sources.

The consortium intends to use those characteristics in developing its proposed computing network, with individual sites contributing capacity according to their infrastructure and operational requirements.

Cooler ambient temperatures can increase the opportunities for data centres to reject heat without relying continuously on mechanical refrigeration.

However, the extent of any energy saving depends on the cooling architecture, server operating temperatures, climate conditions, and other characteristics of the completed facility.

The partners have not disclosed the cooling systems proposed for Oulu, Iru, Valmiera, or the eventual Swedish location.

Electricity access remains a separate requirement. The availability of renewable generation within a region does not automatically establish that a particular property can receive sufficient electricity to operate a large computing facility.

Grid connection agreements, physical supply infrastructure, local network capacity, and the timing of reinforcement work will influence whether each proposed site can proceed.

Neither the total expected electricity demand nor the connection status of the individual facilities has been confirmed.

The consortium also intends to draw on European research expertise. VTT Technical Research Centre of Finland and Sweden’s KTH Royal Institute of Technology are supporting the initiative through research and innovation capabilities.

Their participation is intended to connect the proposed infrastructure with work in advanced computing, semiconductors, AI, and related technical disciplines.

EuroHPC procurement remains unresolved

AI Gigafactory Northern is pursuing an opportunity under the European Union’s AI Gigafactory initiative, which aims to support large computing installations accessible to researchers, public institutions, industry, and other organisations.

The programme is being administered through EuroHPC, which opened its procurement process in July 2026.

The call seeks consortia capable of establishing and operating computing infrastructure, with participating public bodies purchasing access to AI computing capacity through the resulting arrangements.

Under the wider InvestAI initiative, European institutions aim to mobilise approximately €30 billion for AI investment, including €10 billion from EU and national public sources and €20 billion from private investment.

Those figures concern the broader initiative. They do not represent funding allocated or guaranteed to AI Gigafactory Northern.

The procurement is divided into two categories. Large-scale proposals under Lot 2 must be submitted by 3 December 2026, while the deadline for medium-scale proposals under Lot 1 has been extended to 4 February 2027.

EuroHPC also instructed applicants to recreate and resubmit existing tenders following technical problems with the submission system.

DataCentral previously reported the resubmission requirement and the revised procurement arrangements.

The formation of AI Gigafactory Northern is a separate development within that process. The consortium has identified its partners and prospective geographical configuration but has not announced the procurement category under which its final bid will be submitted.

Selection would establish an additional contractual milestone, rather than immediate completion of the proposed computing infrastructure.

Individual development agreements, electricity access, planning permissions, construction arrangements, and financing decisions would still determine the pace of delivery.

AI Gigafactory Northern’s next identifiable milestone is the submission of its proposal under the EuroHPC process. Until the programme selects successful consortia and site-level development details are confirmed, the four-country infrastructure network remains a planned project rather than an operating computing system.