Retelit expands financing package to €425m

Retelit expands financing package to €425m

Retelit has secured additional financing for Italian data centre expansion. UniCredit’s €50m commitment increases an existing €375m facility supporting the construction of new infrastructure in Milan and Rome.

Retelit expands financing package to €425m
Summary
  • UniCredit has extended Retelit Datacenter's existing financing agreement by €50m.
  • The expanded €425m package supports an investment programme targeting 27MW of additional capacity.
  • The financing is separate from reported acquisition interest in Retelit's data centre portfolio.

Italian telecommunications and infrastructure operator Retelit has secured an additional €50m of financing from UniCredit, increasing an existing project finance agreement to €425m as the company’s data centre business progresses its domestic expansion programme.

The additional credit line was arranged through an accordion provision within the original €375m financing agreement, allowing Retelit Datacenter to increase its available borrowing under the existing contractual framework.

UniCredit and ING coordinated the original transaction in March. Its financing structure supports the construction of three data centres in Milan and Rome, targeting a combined 27MW of additional capacity.

The lenders identified an existing capacity base of 18MW when the agreement was established. Delivery of the additional infrastructure would increase that figure to 45MW, assuming the planned developments are completed within the same financing perimeter.

The additional financing was first disclosed on 16 November, with independent legal transaction reporting on 17 November. Its allocation between individual developments and expenditure categories has not been disclosed.

Retelit’s wider development activities include the construction of a 13.6MW data centre at Corsico, southwest of Milan, alongside investment in facilities connected to its existing Avalon campus.

Financing infrastructure construction

The original agreement comprised a €135m term loan, a €225m capital expenditure facility, and a €15m revolving credit facility.

Combining several credit lines allows infrastructure borrowing to accommodate different financial requirements. Term lending provides longer-duration capital, while construction expenditure can be financed progressively as developers reach procurement and installation milestones. Revolving credit provides additional flexibility for shorter-term funding requirements.

UniCredit and ING structured the original agreement as mini-perm project financing, an arrangement commonly used to support infrastructure projects through development and initial operation before a subsequent refinancing.

Such structures can accommodate the changing financial characteristics of a data centre as it progresses from construction into commercial operation. During development, expenditure is concentrated on land, buildings, mechanical installations, and electricity infrastructure. Once computing capacity becomes available to customers, contractual revenues provide a different basis against which lenders can assess the assets.

The additional €50m commitment increases the capital available within Retelit’s existing financing framework without requiring the company to arrange an entirely separate agreement.

Construction of the Corsico development began earlier this year on an approximately 18,000m² site. The project envisages two buildings, with initial capacity expected to become available during 2027.

The Corsico site previously housed steelmaking infrastructure owned by Marcegaglia. Retelit plans to install closed-loop water cooling alongside liquid cooling for computing equipment, and to incorporate provision for heat recovery. The operator also intends to connect the development to its Avalon interconnection network, which serves more than 170 operators and other digital service businesses.

Retelit also disclosed a €100m investment in two facilities within Milan’s Bisceglie district in February. Those buildings would be integrated with the existing Avalon3 data centre, forming a hub with a total power capacity of 10MW.

Expansion around existing telecommunications and interconnection infrastructure allows operators to build on established network relationships while accommodating customers requiring additional computing capacity.

The electrical and mechanical infrastructure serving new buildings must nevertheless be delivered alongside the networking environment, with the availability of sufficient electricity remaining a central development requirement.

Investment and potential ownership changes

Retelit’s expansion follows several acquisitions that have increased its presence within Italy’s telecommunications and digital infrastructure markets.

The company acquired Irideos in 2022 and subsequently purchased BT’s Italian digital infrastructure operations, adding fibre networks and data centre assets to its portfolio.

The BT transaction included approximately 11,000 kilometres of fibre infrastructure and a portfolio of data centres providing 10MW of total capacity, according to UniCredit’s original financing disclosure.

The resulting infrastructure footprint provides connectivity, colocation, and interconnection services to telecommunications operators, businesses, public administrations, and cloud computing providers.

Separately, Retelit’s data centre business has attracted reported acquisition interest from infrastructure investors and operators.

DataCentral reported on 23 November that Vaultica Data Centers, Ardian, Macquarie, and Rai Way had submitted non-binding offers for the portfolio.

No completed acquisition has been established. The additional financing remains a separate transaction supporting Retelit’s existing investment programme.

Expanding an operating data centre portfolio requires developers to balance construction expenditure against revenues generated by existing facilities, particularly where several projects are progressing simultaneously.

Retelit’s expanded credit agreement provides further capital to support that expenditure. The delivery of its planned capacity additions will depend on the completion of construction, electricity infrastructure, equipment installation, and commissioning work at the individual facilities.


Stay updated with the latest insights and trends in the data centre industry by subscribing to our newsletter.

← Back

Thank you for your response. ✨