Summary
- Stendörren has signed an agreement securing 20 MW of electrical capacity for its Almnäs 5:23 property in Södertälje.
- The company received a building permit for approximately 20,000 m² of data centre floor space in summer 2026.
- The electricity connection is expected during the first half of 2028, with a possible increase to 40 MW identified but not yet secured.
Stendörren Fastigheter has secured 20 MW of electricity capacity for a planned data centre development at Almnäs in Södertälje, Sweden, bringing a permitted project closer to the delivery of its required power infrastructure.
The agreement covers the company’s Almnäs 5:23 property within the Stockholm Syd development area. The electrical connection is expected to be completed during the first half of 2028.
Stendörren obtained a building permit for data centre use during summer 2026. The proposed facility covers approximately 20,000 square metres of gross floor area, establishing a permitted building envelope for the development.
The company has also identified the possibility of increasing electricity capacity to 40 MW over the longer term. That additional capacity has not been secured, and no connection timetable has been provided for an expansion beyond the initial 20 MW.
The signed agreement establishes a contractual milestone rather than an operating electricity supply. Network works must still be completed before the planned capacity can be delivered to the property.
Stendörren has not announced a construction commencement date or identified a data centre customer committed to occupying the proposed facility.
Electrical agreement reduces a development constraint
The availability of electricity is a substantial determinant of whether a permitted data centre can proceed to construction and commercial occupation.
A building permit establishes that a proposed development has satisfied the relevant planning requirements, subject to applicable conditions. It does not ensure that the electricity network can deliver sufficient capacity when the facility is ready to operate.
Stendörren’s agreement addresses that distinction by securing 20 MW of capacity and identifying the first half of 2028 as the expected connection period.
However, the company has not disclosed the connection voltage, the scope of any reinforcement works, the proposed substation arrangement, or the allocation of electricity infrastructure costs between the parties.
The 20 MW figure therefore describes the secured electricity capacity rather than the final IT load that the completed data centre will support.
Servers, storage equipment, and network systems consume only part of a facility’s total electricity supply. Cooling equipment, power conversion losses, and other supporting systems must also be accommodated.
Without a published electrical design and projected power usage effectiveness, the full computing load cannot be calculated reliably from the agreed connection capacity.
Likewise, the permitted gross floor area does not determine the number of racks or the type of computing equipment that can ultimately be installed.
Those characteristics depend on the planned internal layout, electrical distribution, cooling architecture, equipment density, resilience arrangements, and customer requirements.
The connection delivery timetable will influence the sequence of construction and commissioning. Permanent electrical infrastructure must be available for the relevant testing and handover activities before a completed data hall can enter commercial service.
Stendörren has not indicated whether construction will begin before the connection is completed or whether the first phase will include a smaller initial computing deployment.
Existing planning permission supports commercial negotiations
The Almnäs development forms part of Stendörren’s wider property portfolio in the Stockholm and Mälardalen regions, where the company owns and develops commercial and industrial real estate.
Its existing activities include developing properties for identified occupiers, with the commercial terms and timing of projects influenced by tenant demand.
Data centre development introduces additional technical requirements compared with conventional logistics or light industrial buildings, particularly in relation to electricity, cooling, structural loading, connectivity, and operational resilience.
The permitted 20,000 m² building and secured electricity capacity provide two elements needed for discussions with potential data centre operators.
Nevertheless, a tenant’s requirements may influence the eventual configuration of the building, including the location of electrical plant, cooling equipment, service areas, and computing halls.
The announcement does not establish whether the facility will be delivered as a building for a single operator, divided between several customers, or developed using another commercial arrangement.
Stendörren’s possible future increase to 40 MW would require further infrastructure arrangements. Additional capacity could support a larger installation or subsequent development phases, but the company has not disclosed a corresponding revised building programme.
The distinction between secured and potential capacity is especially important when assessing large property developments, since a longer-term expansion opportunity does not represent power already available from the electricity network.
Sweden continues to attract proposed data centre projects, but individual developments face different constraints depending on their electricity connection status, site permissions, and commercial agreements.
Stendörren’s 20 MW agreement gives its Södertälje project a defined next infrastructure milestone, while the permitted floor area establishes the scale of the initial property proposal.
Completion of the electrical connection, confirmation of construction arrangements, and the securing of a data centre occupier will determine when the development can progress from a permitted property opportunity to an operating computing facility.