Summary
- Notice CN0150226FL covers the two-storey DUB98 building and an associated medium-voltage room at Cruiserath Road, Dublin 15.
- Its intended construction start was 20 November, with completion proposed for 31 December 2027.
- The notice is distinct from two earlier campus filings, but does not prove that construction has physically begun or establish the new building's IT capacity.
A third building commencement notice for Amazon Web Services‘ Cruiserath campus in Dublin identifies 20 November as the intended start of construction for another data centre building and its associated electrical infrastructure.
The notice, CN0150226FL, covers a two-storey facility identified as DUB98 and an adjoining medium-voltage room at Cruiserath Road, Dublin 15. The recorded floor area is 20,651m², with completion proposed for 31 December 2027.
The filing was submitted to Fingal County Council on 5 November, according to building control information reproduced by Irish construction and infrastructure data services.
The intended commencement date has now passed, but a building control notice is not independent confirmation that contractors began work on site on that date. Actual construction activity and progress against the proposed timetable have not been separately established.
The development forms part of an established data centre campus associated with AWS. Its underlying planning application, FW22A/0308, was submitted by Universal Developers LLC.
Fingal County Council granted permission for the wider development in September 2023. Following an appeal, An Coimisiún Pleanála issued its decision granting permission with conditions on 19 December 2025.
The distinction between the planning applicant and the operator is relevant to understanding the project. Universal Developers LLC is identified in the statutory planning records, while the Cruiserath development has been reported as part of Amazon’s Irish computing infrastructure.
The November filing is not a repeat of the campus’s earlier commencement notices. Records examined by PlanningBrief identify three separately notified buildings under the same planning reference, each with a different description and intended construction timetable.
The first notice, CN0144820FL, concerns DUB108 Data Centre Building F and an associated medium-voltage building. It recorded 20,651m² of works, with an intended start on 10 July 2026 and a proposed completion date of 27 July 2027.
A second notice, CN0148734FL, covers the smaller DUB601 Data Centre Building E development. Its recorded floor area is 1,539m², with an intended start on 12 October 2026 and completion proposed for 15 July 2027.
The latest DUB98 filing therefore represents a further construction phase rather than the resubmission of an earlier building notification.
Different commencement dates can reflect the way a large campus is divided into construction packages. Individual buildings may progress through structural works, electrical installation, mechanical services, testing, and commissioning on separate schedules.
Those schedules can overlap without establishing that every building will become operational at the same time. A planned completion date in a building control notice also does not necessarily describe the date on which computing services will become available to customers.
The inclusion of a medium-voltage electrical room within the DUB98 works identifies an important part of the new building’s supporting infrastructure.
Data centre electrical systems require equipment capable of receiving and distributing power from the campus supply, transforming it to appropriate voltages, and protecting downstream circuits.
Medium-voltage switchgear and associated distribution equipment can provide the connection between higher-capacity campus electrical infrastructure and the transformers, uninterruptible power systems, and lower-voltage distribution networks serving the computing equipment.
The arrangement must also accommodate maintenance and fault isolation while preserving the level of electrical availability required by the facility’s intended operating model.
Protection equipment, redundancy, and the route taken by electricity through the installation therefore influence the amount of capacity that can be reliably delivered to the data halls.
The precise electrical design for DUB98 has not been established from the commencement notice alone. It would be inappropriate to infer the building’s IT load from the size of its medium-voltage room or its overall floor area.
Floor area is a construction measure, while computing capacity depends on the electrical allocation, cooling system, equipment density, and operating requirements of the facility.
A data centre with a substantial building footprint may allocate space to plant rooms, circulation, electrical equipment, and other services rather than computing racks.
Equally, higher-density equipment can support greater IT load within a given floor area if the associated electrical and thermal systems are designed to accommodate it.
The final computing capacity of the additional Cruiserath building has not been disclosed through the available commencement information.
The campus has been developed under earlier electricity connection and planning arrangements. Material considered during the planning appeal described incremental increases in electricity supply negotiated with EirGrid over several years.
Those arrangements indicate that the site’s electricity infrastructure has been planned in stages. They do not establish that all future supply capacity is already energised or available for immediate operation.
Additional computing buildings must be matched to the capacity of the external network and the distribution equipment installed within the campus.
Even when construction reaches practical completion, electrical systems require testing, protection checks, and commissioning before a building can reliably support its intended operating load.
The same applies to mechanical infrastructure. Cooling equipment must remove the heat generated by computing systems while maintaining the temperatures and conditions required for their operation.
Equipment selection, liquid or air cooling arrangements, water requirements, and heat rejection plant can all influence the sequence of installation and commissioning.
Construction work must also account for the facility’s fire protection systems, access arrangements, and operational safety requirements. The new DUB98 notice identifies associated fire safety certification references, but the filing does not establish that every system has been installed or accepted.
The wider Cruiserath campus has an environmental licensing history with the Environmental Protection Agency, reflecting the regulatory requirements associated with its supporting plant and operation.
Environmental permissions and building control notices serve different functions. A commencement notice records a proposed start to construction works; an environmental licence addresses the operation of specified activities and equipment under applicable conditions.
One does not replace the other. New or modified plant may require additional licensing assessment depending on the installation’s circumstances and existing permissions.
Ireland’s electricity connection policy is another part of the development context. The Commission for Regulation of Utilities introduced revised requirements for new data centre connection applicants in December 2025, reflecting the pressures associated with large electricity loads.
Established campuses with earlier connection arrangements may have a different regulatory and contractual position from entirely new developments, although the circumstances of individual projects must be examined separately.
The latest notice adds a verifiable building control milestone to a campus already proceeding through multiple development phases. It identifies the proposed construction works and timetable, but not the final IT capacity or commercial operating date.
The next evidence of physical progress would include confirmation of construction activity, updates to the development programme, and eventually completion and commissioning records for the new building and its supporting electrical systems.