Summary
- Action to Protect Rural Scotland submitted a detailed objection on 19 November concerning the proposed Chapelcross campus.
- The organisation identifies differing IT capacity estimates and conflicting generator numbers within the planning documentation.
- Dumfries and Galloway Council has not determined the application, and consultation on its environmental assessment continues until 29 November.
A formal objection submitted on 19 November has raised detailed questions about the electrical capacity, standby generators, fuel arrangements, and environmental assessment of the proposed Chapelcross AI data centre in Dumfries and Galloway.
Action to Protect Rural Scotland (APRS) has asked the council to refuse application 26/1649/PIP, arguing that gaps and inconsistencies in the supporting documents prevent the consequences of the development from being properly assessed.
The application was submitted by CX Tech Limited for land north of the former Chapelcross nuclear power station near Annan. It seeks planning permission in principle for a major data centre campus, industrial buildings, a training centre, a substation, and associated infrastructure.
The development has been publicly described as a potential 1GW computing campus, although APRS says different documents accompanying the application use different measures of its proposed electrical capacity.
Its objection identifies a sustainability statement assuming eight buildings of 120MW each, equivalent to 960MW in aggregate.
APRS also points to an environmental impact assessment appendix describing 640MW of IT load. The figures have different possible engineering meanings, but the campaign organisation argues that the application does not adequately reconcile them.
The distinction is material because IT load measures electricity consumed by computing equipment, whereas the wider facility requires additional power for cooling, electrical distribution, and supporting infrastructure.
Assessing total electricity demand depends on establishing which figure describes installed computing load, overall operating demand, or another design assumption.
Any calculation of annual electricity consumption would also depend on operating utilisation and the performance of the completed installation. Neither a headline capacity figure nor a planning application establishes the quantity of electricity that will actually be consumed.
APRS has questioned the clarity of the proposed backup generation arrangements. Its submission identifies references to either 312 or 336 generating units in different application documents.
Where the larger figure is used, the organisation says each generator is rated at 3.2MW, producing approximately 1,075MW of aggregate standby generating capacity.
That is a proposed installed power rating rather than evidence that the generators would all operate simultaneously or that the site has permission to use them under unrestricted conditions.
Emergency generation is commonly used to maintain essential data centre operations during interruptions to grid electricity. Its design must account for the transfer of electrical load, the availability of sufficient units during maintenance, and the ability to support critical equipment.
Large installations also require periodic testing, which can create noise and exhaust emissions even when the generators are not being used to supply the facility during an actual outage.
The number of generators and the proposed testing regime therefore influence the technical assessment of air quality, noise, fuel requirements, and operating controls.
APRS argues that the environmental documents do not provide sufficient detail about fuel storage or the final fuel specification for the generating equipment.
The objection also raises questions about references to non-diesel generation and hydrotreated vegetable oil. The campaign organisation is concerned that the documents do not establish a sufficiently consistent account of the intended operating arrangements.
Hydrotreated vegetable oil can be used in compatible compression ignition engines, but its lifecycle environmental characteristics depend on production and feedstock arrangements.
Combustion emissions must still be assessed even when a fuel is classified as renewable. Nitrogen oxides, particulate emissions, and other relevant pollutants depend on engine design, fuel characteristics, exhaust treatment, and operating conditions.
APRS has questioned whether the information supplied adequately establishes the effects of generator testing and emergency operation.
Those concerns are allegations made by an objector, not findings that the development would exceed a particular emissions limit or fail an applicable regulatory requirement.
The organisation has also challenged the scope of the proposed electrical connections and associated infrastructure within the environmental assessment.
Major computing facilities can require substations, high-voltage connections, new cables, and network reinforcement beyond the boundary of their main development site.
Where these assets are essential to the proposed operation, their route, construction effects, and relationship with other energy projects may influence the assessment of cumulative environmental impacts.
APRS argues that the submitted environmental information does not adequately establish how all necessary electrical infrastructure will be considered.
The objection extends to biodiversity and land use. Although the development is associated with regeneration of the former nuclear power station area, the proposed site includes land beyond the former operational station footprint.
APRS disputes whether the development should be characterised as redevelopment of predominantly brownfield land without greater recognition of existing grassland and habitat value.
Its submission refers to environmental documents describing the potential loss of approximately eight hectares of semi-improved neutral grassland and raises concerns about whether proposed habitat creation would adequately address that loss.
Such matters must be assessed using the relevant ecological surveys, statutory consultee responses, and planning policies. The organisation’s objections do not, by themselves, establish the final biodiversity consequences or whether the proposed mitigation would be acceptable.
The scale of public engagement is also significant to the council’s current workload. Dumfries and Galloway Council has confirmed that it is processing more than 10,000 representations concerning the application, the largest volume its planning service has received for a single proposal.
Reports of more than 10,000 representations were already circulating before November. The newer development concerns the authority’s processing and verification arrangements alongside the additional technical objection.
The reported total should not be treated as a verified count of unique individual objectors, because submissions and their classification remain subject to the council’s checking process.
The planning authority has explained that the application seeks permission in principle. If granted, that would establish whether the development is acceptable in principle, while detailed design matters would require subsequent approval.
No planning decision has been made, and the council has stated that it must remain impartial while the application is assessed.
Representations concerning the environmental impact assessment can be submitted until 11.59pm on 29 November, providing a separate consultation period from the original planning application process.
Planning officers will then consider the relevant submissions, the developer’s environmental information, statutory consultee advice, and applicable planning policy.
Further information may be requested where significant matters remain unresolved. The council has stated that any such information would be published and could provide another opportunity for public comment.
A pre-determination hearing is required before the authority reaches a decision on a development of this classification. A committee report and recommendation will also be prepared through the statutory process.
The Scottish Government expects to publish additional guidance concerning data centres in December 2026. The council has confirmed that relevant policy or guidance in force when the application is decided must be considered.
APRS wants the decision-making process to take place with clearer national guidance and more complete technical evidence. The developer’s application remains under assessment, and its claimed economic and infrastructure benefits must be considered alongside the environmental and planning questions raised by consultees.
The next steps are completion of consultation, verification of representations, assessment of the disputed technical information, and publication of the council’s recommendation. Neither the proposed capacity nor the reported generator arrangements have been approved for construction or operation.

