Greystoke sets out £750m Cookham data centre plan

Greystoke sets out £750m Cookham data centre plan

Greystoke Land has released initial plans for a proposed £750m data centre at Cookham’s Lower Mount Farm Industrial Estate, ahead of a public exhibition on 27 November.

Greystoke sets out £750m Cookham data centre plan
Summary
  • Greystoke is proposing to replace existing industrial premises with a data centre and associated landscaped public space.
  • The developer estimates £750m of investment and approximately 75 permanent jobs, although neither figure represents a secured commitment.
  • No planning application has been submitted, and the site's electricity allocation, final IT capacity, and technical specifications remain unconfirmed.

Greystoke Land has released initial visual material for a proposed £750m data centre development at Lower Mount Farm Industrial Estate in Cookham, ahead of a public exhibition scheduled for 27 November.

The Long Lane Data Centre proposal would replace existing industrial premises on land owned by Copas Farms, south of the village in Berkshire. Greystoke is consulting on the development before submitting a planning application to the Royal Borough of Windsor and Maidenhead.

The public exhibition will take place at Pinder Hall, Lower Road, Cookham, between 1.30pm and 8pm on Friday 27 November. Project representatives are expected to explain the emerging designs and answer questions about the proposed redevelopment.

No formal planning application has been submitted, and the initial illustrations do not establish that the buildings have been consented, financed, or scheduled for construction.

The current estate accommodates activities including vehicle storage and repairs, scaffolding, and waste recycling. Greystoke proposes replacing those uses with computing infrastructure and associated landscaping.

The developer has indicated that the project could involve approximately £750m of private investment and support around 75 permanent roles in operations and related services, alongside employment during construction.

Both estimates remain prospective. The actual investment will depend on the final design, utility requirements, procurement arrangements, and whether the development proceeds through planning and commercial approval.

Permanent staffing would depend on the operating model and the services provided at the facility. Construction employment would be temporary and would involve a different range of engineering, building, and specialist installation activities.

Greystoke’s wider proposal includes approximately ten acres of privately owned land south of Long Lane intended to become public parkland. The emerging design describes new planting, ponds, wetlands, walking routes, and landscape features intended to screen the buildings from surrounding areas.

Those elements are proposed community and environmental measures rather than completed works. Their eventual delivery and management would depend on the planning application and any conditions or legal obligations attached to a permission.

The site adjoins Astoria Park, where Bellway is constructing a residential development of approximately 200 homes. Its proximity to existing and future housing makes building height, plant noise, traffic, and the appearance of the development relevant to the planning assessment.

The Cookham Society has already expressed concerns about the potential scale of the proposed buildings and the absence of detailed elevations in the consultation material circulated to residents.

Following earlier discussions with the development team, the society described a possible building approximately 16 metres high and reported that the project had been discussed in terms of around 100MW of computing capacity.

Those figures come from the society’s account of preliminary engagement. Greystoke has not yet published a definitive IT load, electrical connection capacity, or complete set of building dimensions in the available formal project material.

The distinction is important because capacity figures can describe different parts of a data centre’s infrastructure. IT load measures the electricity consumed by computing equipment, while the wider installation also requires power for cooling, electrical distribution, and other building systems.

A proposed 100MW computing facility would require suitable external electrical supply and internal distribution equipment, but the total connection capacity cannot be established without the intended engineering design.

Large data centre developments may need new substations, transformers, high-voltage cable connections, and network reinforcement. The cost and timetable depend on the capacity of the local and wider electricity network and the terms offered by the relevant operator.

No confirmed grid connection agreement or energisation date has been identified for the Cookham proposal. That uncertainty limits the extent to which the project can be treated as prospective deliverable capacity rather than a land development opportunity.

Greystoke has described an intention to use renewable or zero-carbon electricity and to secure that commitment through planning conditions and legal agreements.

The announcement does not identify a completed power purchase agreement, dedicated generating assets, or an hourly electricity matching arrangement. Claims about future renewable electricity procurement therefore remain commitments to be developed rather than verified operating performance.

The proposed cooling design is described as a closed-loop system intended to limit water consumption. Recirculating coolant can reduce the need for continuous water replacement in parts of a cooling circuit, but the overall water and electricity requirements depend on how the system rejects heat.

A closed-loop arrangement may still use dry coolers, mechanical refrigeration, or other plant, and the final operating conditions determine its resource requirements.

Detailed information on the proposed cooling equipment, heat rejection method, and water use has not yet been published. Those characteristics will need to be established through the eventual engineering and environmental submissions.

Standby generators are also expected to form part of the development. Such equipment provides electrical resilience during interruptions to normal supply and normally requires periodic testing as well as maintenance.

Generator location, fuel storage, exhaust arrangements, and testing procedures can influence air quality, noise, safety, and planning conditions, particularly where residential property is nearby.

The Cookham Society has questioned whether the emerging consultation material gives residents sufficient information to assess those impacts. The planning process will require the developer to provide supporting documents capable of being examined by the authority and statutory consultees.

Greystoke has previously advanced other large data centre projects, including proposals at Abbots Langley and West London Technology Park. The company specialises in developing sites and securing the planning and infrastructure arrangements needed for major computing facilities.

Experience with those projects does not establish that the Cookham development will receive permission or secure equivalent electrical capacity. Each site must be assessed against its own land, infrastructure, environmental, and planning conditions.

Greystoke expects to provide further technical and planning information as the proposal develops. The initial consultation is separate from the statutory process that will follow if a formal application is submitted.

The 27 November exhibition will provide an opportunity to clarify the proposed building envelope, electricity and cooling assumptions, and the treatment of existing industrial uses.

Until those details are established, the project remains an early proposal. Its investment estimate and indicative computing scale should not be included in calculations of consented, connected, or operating UK data centre capacity.


Stay updated with the latest insights and trends in the data centre industry by subscribing to our newsletter.

← Back

Thank you for your response. ✨