Summary
- Ellevio is rebuilding switchgear at Kvarnsveden and expanding regional electricity infrastructure serving Borlänge.
- The regional network programme will increase the number of power lines connecting Repbäcken and Kvarnsveden from two to four.
- Svenska kraftnät expects its separate 400kV transmission connection between Bäsna and Repbäcken to enter service in 2031 or 2032.
Swedish electricity network operator Ellevio is rebuilding electrical infrastructure around Borlänge to support the development of computing facilities at the former Kvarnsveden industrial site, with the wider network reinforcement programme scheduled to continue until 2032.
The works include rebuilding switchgear at Kvarnsveden, expanding the Repbäcken regional substation, and increasing the number of power lines connecting the two locations from two to four.
Repbäcken’s reconstruction is scheduled to run from autumn 2026 until summer 2029. Further regional network improvements are expected to follow, including additional 145kV infrastructure and changes to electricity distribution arrangements around Borlänge.
The programme, detailed in project information updated on 20 November, is being developed alongside a separate transmission network reinforcement led by Sweden’s national electricity transmission operator, Svenska kraftnät.
Its proposed additional 400kV line between Bäsna and Repbäcken is expected to enter service in 2031 or 2032. Svenska kraftnät submitted its application for permission to construct and operate the line in May 2026, with construction targeted for 2029 or 2030.
Ellevio has also submitted applications for new regional electricity lines, involving combinations of overhead conductors and underground cables. The final construction sequence remains dependent on the progression of the relevant network authorisations and engineering works.
Computing development advances alongside grid investment
EcoDataCenter is developing computing facilities at Kvarnsveden, where its partnership with French AI developer Mistral AI forms part of a stated €1.2bn long-term investment in Swedish digital infrastructure.
The companies detailed their collaboration in February 2026. Mistral’s facility is intended to open in 2027, several years before the completion of Ellevio’s wider network reinforcement programme.
Mechanical and electrical installation work is also progressing at the industrial site. Swedish technical services contractor Bravida secured a SEK650m contract in July covering electricity and industrial pipework at another EcoDataCenter development in Kvarnsveden.
The differing timetables reflect the phased relationship between data centre construction and electricity network expansion. Individual computing facilities can potentially operate using existing or intermediate electrical infrastructure while longer-term reinforcement enables subsequent development.
Ellevio’s published timetable therefore does not establish that computing operations at Kvarnsveden must wait until 2032. Nor does it specify the amount of additional electrical capacity that will ultimately be allocated to individual facilities.
Regional networks depend on transmission reinforcement
The 145kV lines serving Borlänge form part of the regional infrastructure through which electricity is distributed from the national transmission system to local consumers.
Increasing the number of connections between substations can improve the amount of electricity that can be carried and provide greater flexibility in network operation. The actual improvement depends on equipment ratings, electrical protection arrangements, available transformer capacity, and constraints elsewhere in the network.
An additional regional power line cannot necessarily resolve a shortage of electricity arriving through the higher-voltage transmission system. Reinforcement may be needed at several points along the connection before the complete network can accommodate substantial new demand.
Svenska kraftnät’s planned 400kV line between Bäsna and Repbäcken addresses that wider requirement. Its development also demonstrates why the electricity infrastructure serving large industrial and computing projects can take considerably longer to deliver than individual buildings.
Transmission lines require route assessment, environmental examination, regulatory authorisation, land arrangements, and specialist electrical engineering. Construction must also be coordinated with existing networks, particularly where new equipment will connect to substations already supplying other customers.
Former industrial sites such as Kvarnsveden can offer developers access to established electricity infrastructure and land previously used for energy-intensive activities. However, their conversion to computing facilities still requires network operators to assess the characteristics and scale of new demand.
AI computing installations may introduce different load profiles and electrical protection requirements from those of the industrial equipment previously occupying a site.
The regional electricity programme will consequently serve more than a single construction project. Its completion is intended to increase the network’s ability to accommodate anticipated demand around Borlänge, while individual data centre developments progress according to their own connection and construction arrangements.
The commissioning of each successive electrical reinforcement will determine how that expansion can be accommodated before the additional national transmission connection becomes available.