Summary
- The Bidder Street development in Canning Town has been sold to an undisclosed purchaser for an undisclosed amount.
- The site has detailed planning permission and approximately 130MVA of reserved electricity capacity.
- Goldacre now estimates potential IT capacity of 90MW, although construction, energisation, and commissioning remain outstanding.
Goldacre Ventures and Legal & General have sold a consented data centre development site in East London with approximately 130MVA of reserved grid capacity and potential to accommodate 90MW of IT equipment.
Goldacre confirmed the transaction on 19 November following a development programme that began when the two investors partnered in 2020. The purchaser and sale price have not been disclosed.
The site is located at Bidder Street in Canning Town, within the London Borough of Newham. It occupies former industrial land that has undergone planning, remediation, and enabling works in preparation for a large computing facility.
The sale transfers development rights and a substantially prepared site rather than an operational data centre. The proposed buildings have not been commissioned, and the reserved electricity capacity is not evidence that the full intended load is already energised.
Goldacre says the project has detailed planning permission and a pathway to delivering approximately 90MW of IT capacity within this decade.
The latest figure differs from earlier project material, which described an 80MW hyperscale development when the scheme obtained planning approval in October 2024.
The original design was developed by specialist data centre architect TTSP in collaboration with Foster + Partners, working with the development team and its financial backers.
Goldacre’s November account places the potential computing capacity at 90MW. It does not explain the engineering revisions behind that figure or establish whether the full increase has been reflected in subsequent detailed design documentation.
The distinction between design capacity and operational capacity remains important. A completed data centre cannot operate at its intended IT load until the electrical, cooling, network, and supporting systems have been installed, tested, and commissioned.
Goldacre identifies approximately 130MVA of reserved grid power as one of the principal assets assembled during the development programme.
Megavolt-amperes measure apparent electrical power, whereas megawatts measure active power. Their relationship depends on the electrical power factor, so 130MVA should not be reported as 130MW of usable computing capacity.
A data centre’s external electricity requirement also exceeds the consumption of its servers and networking equipment. Cooling machinery, pumps, fans, power conversion losses, lighting, and other building services contribute to the total load.
Those additional requirements help explain why a development described as having 90MW of IT potential may seek a larger electricity allocation. The exact engineering margins depend on the selected equipment and final facility design.
Securing a reservation of this scale is a substantial development milestone in London, where new computing facilities compete with other industrial and commercial electricity users for available network capacity.
New electrical connections may require reinforcement of substations, installation of high-voltage equipment, additional cable routes, and agreements with the relevant network operator.
Even where capacity has been reserved, developers must still complete the associated works before relying on the connection for commercial operation. The date on which power becomes available can determine when the building and its computing equipment begin generating revenue.
Goldacre reports that the development team secured land and power rights, obtained the necessary planning permission, completed site remediation, and advanced enabling works.
Those activities reduce some of the uncertainties facing a new owner, although they do not remove construction costs, procurement requirements, or the need to establish a commercially viable operating model.
The previous development programme was associated with an estimated £750m investment. That figure describes the proposed capital cost of delivering the data centre and must not be treated as the undisclosed consideration paid for the site in November.
Previous planning material describes an urban development combining computing accommodation, electrical infrastructure, offices, and supporting mechanical plant.
Unlike a remote campus with substantial undeveloped land, a large data centre in a dense urban setting must accommodate major electrical and mechanical systems alongside existing roads, buildings, and neighbouring development proposals.
Design work therefore includes service access, equipment delivery routes, emergency generation, cooling plant, structural loading, and the effects of operating equipment on surrounding uses.
The project has also been associated with proposals to recover heat from computing equipment for potential use by neighbouring buildings.
Heat recovery infrastructure can capture thermal energy from the cooling system, but delivering it to customers requires heat exchangers, distribution pipework, suitable temperatures, and an operating arrangement with the receiving network.
Earlier planning reporting indicated that the facility was being designed to allow heat recovery without confirming construction of the district heating network required to distribute that heat to nearby residents.
The ability to recover heat is therefore a design feature, not evidence that the project is already providing heating or that a local network has been financed and commissioned.
Newham’s wider redevelopment plans form part of the site’s planning context. The data centre was designed in coordination with neighbouring development proposals in the Cody Triangle area, including public realm and access considerations.
Goldacre says the consented scheme will contribute to local regeneration through infrastructure investment and public realm improvements. The delivery and extent of those benefits will depend on the approved conditions and the development programme pursued by the purchaser.
The location also provides access to London’s established telecommunications and interconnection market. Fibre connectivity and proximity to customers can support demand for additional data centre space, particularly where a facility offers substantial electrical capacity.
However, the sale announcement does not identify a committed occupier, confirmed computing hardware configuration, or lease arrangement covering the projected IT load.
Consequently, the transaction establishes a change in ownership of a prepared development opportunity, not a confirmed increase in London’s operating data centre capacity.
The purchaser must determine the construction and financing programme, complete the remaining infrastructure works, and secure any required commercial arrangements before the project can enter service.
Goldacre’s statement describes the electrical capacity as expected to be energised within this decade. A more precise energisation date, construction start, and commissioning schedule have not been publicly confirmed.