Google halts Belgian data centre construction

Google halts Belgian data centre construction

Belgian authorities have ordered Google to suspend data centre construction. The intervention follows a dispute over amended planning permission, including changes to the development’s building configuration, cooling systems, and proposed…

Google halts Belgian data centre construction
Summary
  • Walloon authorities have intervened to suspend construction at Google's development near Charleroi.
  • Amended plans included consolidating two buildings and introducing cooling infrastructure drawing water from the Sambre.
  • A public hearing concerning Google's planning appeal is scheduled for 7 January 2027.

Google has suspended construction at its data centre development in southern Belgium after Walloon authorities intervened over the company's amended planning permission, bringing a dispute concerning building design and water consumption into the construction programme.

The intervention affects Google's development at the Ecopôle business park, near Charleroi, where construction continued following the cancellation of an amended development permit in August.

Google maintains that the works undertaken were authorised under its existing permissions but has suspended the affected activity pending further guidance from regional authorities.

The original permit, granted in 2024, covered three data centre buildings using air cooling. Google subsequently sought to consolidate two of those buildings and introduce cooling infrastructure drawing water from the nearby Sambre river.

Regional administrators approved the amended proposals in April 2026. However, Walloon minister François Desquesnes overturned that decision in August following an appeal by residents.

Environmental organisation Greenpeace requested urgent regulatory intervention last week after investigating reports that construction was continuing. Google separately lodged an appeal against the ministerial decision with Belgium's Council of State on 17 October, with a public hearing scheduled for 7 January.

The dispute centres partly on the extent to which changes in mechanical infrastructure alter the environmental characteristics of an otherwise permitted development.

Water availability and thermal design

Google's amended application envisaged drawing up to 600 cubic metres of water per hour from the Sambre. Material published by the Walloon Parliament indicates that less than a quarter of the proposed abstraction volume would have been returned to the river.

Those figures concern the proposed design rather than measured operating consumption. Nevertheless, the anticipated difference between abstraction and return volumes establishes why regulators are examining the consequences for local water availability.

Water abstraction introduces operational dependencies that extend beyond the performance of the cooling equipment itself. River flow, water temperature, competing industrial requirements, and restrictions during drought conditions can all influence the availability of water for heat rejection.

Where those conditions limit the capacity of external cooling infrastructure, operators may need alternative heat rejection arrangements or restrictions on the computing equipment they can operate simultaneously.

The use of liquid cooling within a data centre does not necessarily require substantial water consumption. Heat can be transferred from processors into closed coolant circuits and subsequently rejected through dry cooling equipment, reducing dependence on external water supplies.

However, dry cooling performance depends on ambient temperatures and the operating characteristics of the equipment. Designs incorporating evaporative cooling can provide different electrical efficiency and thermal performance characteristics, at the expense of greater water requirements.

Selecting between these arrangements consequently involves a site-specific assessment of electricity availability, climatic conditions, water resources, and anticipated computing densities.

Google's revised Belgian plans brought those engineering decisions back within the scope of a contested environmental assessment after the original development had obtained permission.

Construction and procurement exposure

Changes to a data centre's cooling architecture can affect far more than the specification of individual mechanical components. Pumping infrastructure, pipework, external plant, water treatment equipment, building layouts, and electricity distribution may all require corresponding modifications.

Where construction has already begun, those changes can introduce additional coordination requirements between civil engineering contractors, mechanical specialists, electrical equipment suppliers, and the developer's own engineering teams.

A suspension of construction also creates uncertainty around procurement commitments. Equipment ordered against an anticipated construction programme may require alternative delivery arrangements, storage, or revisions to installation schedules.

The financial consequences of the Belgian intervention have not been disclosed. Nor has Google established whether the suspension will affect its wider infrastructure delivery timetable.

Elsewhere in Europe, the company has encountered separate environmental scrutiny over its proposed Finnish development at Muhos, where police opened an investigation into suspected environmental damage earlier this month.

Although the legal circumstances differ, both cases demonstrate the exposure of large computing infrastructure projects to local environmental conditions and the permissions governing their construction.

A development's permitted building footprint cannot necessarily be separated from the mechanical infrastructure required to support it, particularly when revisions alter the volume of water abstracted or the conditions under which it can be discharged.

Google's appeal will now establish whether the disputed ministerial decision can be overturned. Until the planning position is resolved, the company faces uncertainty over the construction programme and the cooling configuration that its completed Belgian facility will ultimately accommodate.