Summary
- MPs approved the National Policy Statement for Data Centres Committee on 18 November, appointing Toby Perkins as chair.
- The committee will examine the draft framework governing data centre developments entering England's nationally significant infrastructure planning regime.
- Public consultation closes on 8 January 2027, and the policy statement has not yet been finalised.
MPs have approved the creation of a parliamentary committee to scrutinise England’s proposed National Policy Statement for Data Centres, establishing a dedicated examination of the framework intended to guide planning decisions on major computing infrastructure.
The House of Commons agreed the committee’s establishment on 18 November, following a recommendation from the Liaison Committee. Labour MP Toby Perkins has been appointed chair.
The committee will examine the initial proposal for the National Policy Statement, laid before Parliament on 28 October, and make recommendations under Standing Order No. 152H.
Its establishment is a procedural decision rather than approval of the proposed policy. The draft remains subject to consultation and parliamentary scrutiny before any final statement can take effect.
The Government published the draft framework as part of its approach to enabling major data centre developments to use the Nationally Significant Infrastructure Projects (NSIP) consenting regime in England.
Public consultation remains open until 11.59pm on 8 January 2027. The committee’s work will provide a separate parliamentary examination of the proposed arrangements.
The draft sets out how applications proceeding through the NSIP regime should be assessed, including their infrastructure requirements and environmental, social and economic effects.
Data centre proposals can involve substantial electricity demand, large technical buildings, cooling installations and connections to networks extending beyond the development site. The framework seeks to establish how those requirements should be considered when determining nationally significant applications.
Committee will examine the proposed planning framework
The Commons resolution appoints 14 members to the National Policy Statement for Data Centres Committee.
They are Dan Aldridge, Julia Buckley, Alistair Carmichael, Christopher Chope, Lizzi Collinge, Andrew Cooper, Helena Dollimore, Ben Goldsborough, Ruth Jones, Chi Onwurah, Toby Perkins, Mike Reader, Blake Stephenson and Henry Tufnell.
The committee’s responsibility is to consider the draft policy statement and make recommendations. It is not a planning authority determining individual data centre applications.
National policy statements establish the considerations relevant to major infrastructure decisions taken through the applicable development consent process.
They can set out the need for particular infrastructure and the balance between development objectives and the effects of individual proposals.
The draft data centre statement includes proposals addressing project scale and the circumstances in which developments may proceed through the nationally significant infrastructure regime.
One subject under consultation is an indicative threshold of 100MW of rated IT load. The Government is seeking views on whether that is an appropriate measure for identifying developments of sufficient scale.
Rated IT load describes a computing capacity specification rather than the total electricity consumed by an operating facility. The complete installation may also require electricity for cooling, power distribution and other supporting services.
The proposed threshold is not an existing universal planning requirement for all English data centres, and the consultation may result in changes before the framework is finalised.
Developers seeking the NSIP route must also satisfy the applicable statutory and procedural requirements. Publication of a draft policy statement does not automatically transfer every data centre application out of local planning arrangements.
Energy, water and local impacts remain under examination
The draft framework addresses infrastructure requirements that can influence both the location and viability of a data centre development.
Electricity availability is an important consideration because large facilities may depend on new substations, network reinforcement or other power infrastructure before they can operate at their intended capacity.
Planning permission for the computing buildings is separate from the practical delivery of those electricity connections. A development consent decision does not independently establish that all necessary electrical works have been completed.
Cooling arrangements can also influence project design and local resource requirements. Depending on the selected equipment and heat rejection method, a facility may require substantial mechanical installations and additional water infrastructure.
Environmental assessment must consider the circumstances of the particular proposal, including its effects on the surrounding area and the adequacy of mitigation measures.
Large technical buildings can introduce questions about landscape, visual impact, construction traffic and the relationship between industrial infrastructure and neighbouring communities.
Backup generators may create further considerations concerning noise, emissions and operating restrictions, although the precise effects depend on the equipment and conditions proposed.
The draft statement is intended to provide a consistent national framework for assessing such factors where applications proceed through the NSIP system.
Consistency does not remove the need for project-specific evidence. The acceptability of one development cannot be established solely by reference to another site’s electricity capacity or cooling arrangements.
The Government has separately introduced a Data Centre Covenant setting out expectations for responsible development, including commitments relating to electricity use, environmental performance and local benefits.
Those policy initiatives form part of the context for the draft National Policy Statement, but neither constitutes permission to build an individual facility.
Parliamentary scrutiny will provide an opportunity to examine whether the proposed assessment criteria adequately reflect the infrastructure and community effects associated with large developments.
Consultation responses from developers, infrastructure providers, local authorities, technical specialists and affected communities will also inform consideration of the final framework.
The committee was formally established on 18 November and will now undertake its examination under the terms approved by the Commons.
Its recommendations, together with the public consultation and the Government’s subsequent decisions, will determine how the proposed planning framework develops before any final National Policy Statement is adopted.