Summary
- Nordic countries accounted for 49% of European data centre leasing activity during 2026 to the end of September.
- Frankfurt, London, Amsterdam, Paris, and Dublin collectively accounted for 23% of leasing activity.
- Global vacancy has fallen from 3.5% to 1.8%, despite substantial expansion in built and preleased infrastructure.
Nordic countries have overtaken Europe’s established metropolitan data centre markets in new leasing activity, according to third-quarter research from DatacenterHawk, as large computing installations increasingly secure capacity outside the continent’s traditional colocation hubs.
The research attributes 49% of European leasing activity during the first three quarters of 2026 to Nordic markets. Frankfurt, London, Amsterdam, Paris, and Dublin — collectively known as FLAPD — accounted for 23%.
The geographical shift accompanies a substantial increase in global colocation capacity. DatacenterHawk’s research, published on 16 November, puts its measure of built or preleased capacity at approximately 77.6GW, compared with 51GW recorded for 2025.
Global vacancy has nevertheless fallen from 3.5% to 1.8%. The decline indicates that new supply has been accompanied by considerable commercial demand, including commitments for facilities that are not yet operational.
The report draws on data covering more than 11,000 facilities across 460 markets. Its headline capacity figure incorporates preleased infrastructure and should not be interpreted as representing 77.6GW of computing equipment already available for customer use.
Separate third-quarter research from property adviser CBRE puts vacancy across the five FLAPD markets at 5.8%, a decline of 2.2 percentage points from the preceding quarter. Although the two reports use different geographical and methodological boundaries, the CBRE findings indicate that availability within Europe’s established markets also remains under pressure.
Electricity availability influences leasing decisions
Large AI training deployments have increased demand for contiguous computing capacity, particularly where customers require tens or hundreds of megawatts within a single installation.
Such requirements can be difficult to accommodate within mature metropolitan markets where developers compete for industrial land and electricity network capacity alongside existing commercial and residential infrastructure.
Some training workloads offer greater flexibility over their geographical location than applications requiring immediate proximity to end users or established network exchanges. Developers can therefore consider locations further from major metropolitan centres, provided that sufficient connectivity and electricity are available.
Nordic markets offer a combination of established low-carbon generation, industrial development land, and climatic conditions that can support certain cooling architectures. The commercial value of those advantages, however, varies considerably between individual sites.
Regional electricity generation cannot independently establish the capacity available through a particular substation. Developers must account for transmission constraints, local network equipment, and commitments already made to other electricity consumers.
Projects may also require new substations, transformers, and power lines before they can accommodate their intended computing installations.
DataCentral’s recent coverage of proposed distributed AI infrastructure across the Nordic region illustrates how developers are exploring alternatives to concentrating substantial new demand within a single metropolitan market.
The expansion of Nordic leasing does not necessarily indicate a corresponding contraction in the infrastructure requirements of established European hubs. Frankfurt and London retain extensive telecommunications networks, enterprise customers, and financial services infrastructure whose proximity can remain commercially important.
Rather than serving identical workloads, emerging Nordic campuses and established metropolitan facilities can accommodate different combinations of computing, storage, and connectivity requirements.
Contracted demand precedes infrastructure delivery
Preleasing provides developers with commercial commitments that can support financing and construction decisions before a facility becomes operational.
The value of those commitments depends partly on the delivery conditions agreed between developers and customers. A data centre may have a substantial proportion of its proposed capacity contractually allocated while still awaiting construction, electrical connections, or mechanical commissioning.
Long electricity infrastructure development periods can create a considerable interval between the signing of a lease and the availability of the associated computing capacity.
Developers must also accommodate changes in customer hardware requirements during that period. An installation initially designed around one generation of computing equipment may require changes to its electrical distribution or cooling architecture before the customer takes occupation.
The growing scale of those commitments places additional importance on the distinction between leased, energised, and operational capacity when assessing infrastructure markets.
A region attracting substantial preleasing activity may subsequently experience rapid construction growth, but its ability to convert that demand into operating facilities will depend on the progression of individual development programmes.
DatacenterHawk’s figures indicate that the Nordic countries are securing a growing proportion of Europe’s new commercial commitments. The next measure of their expansion will be the amount of contracted infrastructure that progresses through permitting, electricity connection, construction, and customer acceptance.