Summary
- Tract has circulated initial proposals for Stockton-on-Tees Technology Park, encompassing up to 13 data centre buildings.
- Stockton West MP Matt Vickers says more than 4,000 people have signed a petition opposing the development.
- The proposed investment and employment figures remain indicative, with a formal planning application yet to be submitted.
American data centre developer Tract is facing opposition to its proposed Stockton-on-Tees Technology Park, where initial development plans envisage a campus of up to 13 data centre buildings on agricultural land near existing residential areas.
Stockton West MP Matt Vickers confirmed on 24 November that more than 4,000 people had signed a petition opposing the proposed location between Hartburn, Fairfield, and Elton.
The development, reported as representing a potential £10.3bn investment, would occupy land on the western edge of Stockton. Initial plans include a logistics building, an electricity substation, internal roads, landscaping, two principal vehicle accesses, and a separate emergency access.
Tract has circulated development information to local residents, outlining an indicative construction programme extending over approximately eight years.
The developer’s published proposals have been reported as forecasting up to 1,500 construction jobs and a further 1,250 supply chain jobs annually during the development period, followed by around 400 permanent data centre positions and additional employment supported through the supply chain.
Those estimates represent anticipated economic benefits rather than confirmed employment commitments. The council has yet to receive a formal planning application, and the development’s final scale remains subject to subsequent commercial, engineering, and planning decisions.
Vickers is advocating the use of previously developed industrial land instead of the proposed greenfield site. Tract’s position, as reported in local development coverage, is that available brownfield locations in Stockton do not meet the requirements of a campus of this size.
Land and electricity requirements constrain site selection
Large computing campuses require sufficient contiguous land to accommodate more than their principal buildings. Electrical substations, mechanical equipment, logistics infrastructure, access roads, drainage arrangements, and construction compounds can occupy substantial areas of a development site.
A previously developed industrial location may offer access to established electricity infrastructure and transport connections, but its suitability will depend on the physical configuration and condition of those assets.
Existing buildings, contamination, underground services, and restrictions arising from previous land uses can complicate the development of brownfield locations. Remediation and utility relocation may also increase construction costs or extend the period before a site can accommodate new infrastructure.
Greenfield development can provide greater flexibility over the arrangement of buildings and supporting equipment, particularly where developers intend to construct facilities in several phases. However, it introduces competing considerations concerning agricultural land, landscape character, biodiversity, and neighbouring communities.
Electricity availability is another constraint that can limit the number of viable alternative locations. A site with sufficient land may remain unsuitable if its intended power requirements cannot be accommodated within the surrounding electricity network.
Although Tract’s initial Stockton proposals include an on-site substation, the available information does not establish the final electrical capacity of the development or the timing of connections serving individual data centre buildings.
Tract is separately developing plans for Durham Technology Park, a proposed seven-building campus with an electricity requirement of up to 500MW. That development is located near South Hetton, Murton, and Easington Lane and remains distinct from the Stockton proposals.
Economic benefits and local impacts
An eight-year construction programme would create an extended period during which neighbouring communities could experience changing volumes of construction traffic, noise, and temporary disruption.
The long-term effects would depend on the final buildings and equipment installed. External mechanical plant, emergency generation, electrical substations, and the movement of maintenance personnel can all influence the operational characteristics of a completed campus.
Those details will require assessment through the planning process, alongside the development’s transport requirements, environmental effects, and proposed mitigation measures.
The economic case also needs to distinguish construction employment from the permanent workforce required to operate the completed facilities.
Tract’s indicative figures anticipate a substantial reduction in direct employment once construction ends, although additional economic activity could arise through maintenance contracts, equipment supply, security, and other supporting services.
The developer has also projected substantial future business rates income from the campus. The amount ultimately generated would depend on how much infrastructure is built, its rateable value, the timing of occupation, and the applicable local government funding arrangements.
Neither the proposed investment value nor the projected economic contribution resolves the question of whether the selected location is appropriate.
The petition establishes the extent of organised opposition before the formal planning process has begun. Tract must still develop its proposals into an application through which the local authority can examine the site’s suitability, its infrastructure requirements, and the relationship between the proposed campus and surrounding land uses.