Summary
- PACE DC proposes a data centre campus near Milton Ernest and Thurleigh, with a public consultation scheduled for 18 November.
- The development would connect to a consented 49.9 MW solar farm and 69 MW/138 MWh battery storage scheme, while retaining access to grid electricity.
- The data centre has not secured planning permission, and its eventual IT load, construction timetable, and operating energy requirements have not been confirmed.
PACE DC is consulting on proposals for a data centre campus covering approximately 22 hectares in Bedfordshire, designed to operate alongside a consented solar farm and battery storage development.
The proposed Thurleigh Road Data Centre would occupy land between Milton Ernest and Thurleigh, north of Bedford. Preliminary plans indicate a campus with four data centre buildings, supporting electrical and mechanical infrastructure, access arrangements, and landscaping.
The developer is holding a public consultation at Milton Ernest Village Hall on 18 November, from 4pm to 8pm, ahead of submitting a planning application to Bedford Borough Council.
PACE DC is part of Pathfinder Clean Energy, a UK renewable infrastructure developer involved in the neighbouring electricity generation and storage projects.
Those projects have already received planning permission, but the proposed data centre has not. Its construction will require a separate planning decision, which the developer is targeting for summer 2027.
The data centre’s planned IT capacity, total electrical connection requirement, and construction budget have not been disclosed.
Solar generation would connect directly to computing infrastructure
The development would be located next to a consented 49.9 MW solar farm and a battery energy storage system rated at 69 MW with 138 MWh of storage capacity.
PACE DC intends to connect the facilities through a direct electrical arrangement, allowing locally generated electricity to supply part of the data centre’s demand when sufficient solar output is available.
Grid electricity would provide additional supply when required, according to the developer’s emerging plans.
The electrical relationship between the three facilities remains subject to detailed design. PACE DC has not disclosed the proposed grid import capacity, the operating schedule of the battery system, or the expected proportion of the data centre’s annual consumption supplied by the solar installation.
A solar farm’s installed generating capacity does not indicate continuous electricity availability. Output changes with daylight, cloud cover, season, and other operating conditions, while generation ceases overnight.
Battery storage can move electricity between periods of generation and demand, but the storage system’s power and energy ratings describe different characteristics.
The proposed battery installation is rated at 69 MW, indicating its nominal power capability, and 138 MWh, describing its nominal stored energy capacity.
Neither figure establishes how much electricity the system would supply to the data centre, how frequently it would operate, or what portion of its capacity would be allocated to other electricity market activities.
Data centres require continuous electricity for computing, cooling, power distribution, and other supporting systems. The proposed grid connection would therefore remain an important component of the site’s electricity arrangements.
PACE DC has not published the completed power architecture, including how the data centre’s uninterruptible power systems and emergency supply arrangements would interact with the neighbouring energy storage development.
A battery installation associated with a solar farm is not automatically equivalent to the dedicated power protection and resilience infrastructure required for critical computing equipment.
Cooling design aims to limit water consumption
PACE DC is proposing a closed-loop water cooling system intended to avoid continuous water consumption through evaporation.
The concept involves circulating water through the cooling system to collect heat from the computing infrastructure before transferring that heat through chillers or dry coolers.
The cooled water would then return through the system, reducing the need for replacement water under normal operating conditions.
Actual water consumption will depend on the final engineering configuration, including any supporting water systems, maintenance requirements, and losses from the completed installation.
The developer also intends to make recovered heat available to neighbouring homes or businesses where a suitable distribution network can be established.
Heat reuse would require a customer with an appropriate heating demand, equipment capable of transferring heat at a useful temperature, and the necessary distribution infrastructure.
No completed heat supply agreement or district heating connection has been identified for the proposal.
The developer’s stated cooling and energy arrangements are design intentions rather than measured performance from an operating facility.
Planning will determine the development’s final form
The proposed campus lies within a rural area close to several established villages. Its planning application will need to address the effects of construction and operation on neighbouring land uses and local infrastructure.
PACE DC has identified traffic, ecology, landscaping, and visual effects among the subjects to be discussed during consultation.
The final application will also need to establish the scale and positioning of buildings, access arrangements, electrical infrastructure, and the environmental characteristics of the proposed operation.
The developer intends to provide at least 10% biodiversity net gain through ecological measures associated with the site, although the detailed arrangements have not been finalised.
Economic projections published for the scheme include approximately 1,500 direct construction jobs and up to 1,900 additional supply chain roles during development.
PACE DC also estimates that the completed facility could support 80 full-time-equivalent operational jobs and generate between £2.5 million and £3.5 million in annual business rates for Bedford Borough Council.
Those estimates are provisional. The developer states that a detailed economic impact assessment is still being prepared, and the final employment and revenue figures will depend on the development’s approved scale and delivery.
The company has also proposed establishing a community benefit fund, with its structure and possible uses to be developed following engagement with local residents.
PACE DC expects to submit its planning application before the end of 2026, with a decision anticipated during summer 2027.
The existing permissions for solar generation and battery storage provide a potential basis for the proposed energy arrangements, but they do not authorise construction of the data centre.
The public consultation and subsequent planning submission will establish the final development footprint, the intended electricity requirements, and the extent to which the proposed computing infrastructure can be integrated with the neighbouring energy facilities.