Pace proposes solar-linked Bedfordshire data centre

Pace proposes solar-linked Bedfordshire data centre

Pace DC is developing plans for a Bedfordshire computing campus. The proposed development would connect directly to an approved solar farm and battery storage installation, with a planning application expected…

Pace proposes solar-linked Bedfordshire data centre
Summary
  • Pace DC proposes developing a computing campus on approximately 22 hectares near Milton Ernest.
  • The adjoining energy developments include a 140MWp solar installation and 69MW/138MWh battery storage system.
  • Pace DC intends to retain long-term ownership and operational responsibility for the data centre.

Renewable energy developer Pathfinder Clean Energy is pursuing a data centre campus in Bedfordshire through its Pace DC business, proposing a direct electrical connection to solar generation and battery storage facilities for which planning permission has already been secured.

The proposed development would occupy approximately 22 hectares of land off Thurleigh Road, between Milton Ernest and Thurleigh, within the administrative boundaries of Bedford Borough Council.

Pace DC presented its plans at a public consultation on 18 November and expects to submit a planning application before the end of the year. Its published development timetable anticipates a council decision during summer 2027, following preliminary discussions with planning officers earlier this year.

The company intends to retain ownership and responsibility for operating the computing infrastructure rather than selling the development once planning and electricity arrangements have been established.

Buildings would occupy only part of the proposed site, with land also allocated to landscaping, access roads, and supporting infrastructure. The developer has not disclosed the intended computing capacity or total electricity demand.

Pathfinder secured planning permission in February for the adjacent solar farm, which has a proposed installed photovoltaic capacity of 140MWp and a grid export rating of 49.9MW. The development would share infrastructure with the previously approved Thurleigh Road battery storage project.

The first phase of the storage installation, for which Pathfinder obtained planning consent in January 2024, is designed to provide 69MW of discharge power and 138MWh of energy storage. Its original purpose includes providing balancing services to the electricity system.

Integrating generation and electricity consumption

A direct connection would allow the data centre to consume locally generated electricity when it is available, while retaining access to the wider electricity network. The extent to which local generation could meet its demand cannot yet be established because the developer has not published an electrical load profile.

The distinction between the solar installation’s photovoltaic rating and its grid export rating is important when assessing the combined development. The former describes the nominal peak output of the installed modules, while the latter describes the rated power that can be exported through its grid connection.

Neither figure establishes the amount of electricity that the data centre would receive. Solar output varies with daylight, weather conditions, and seasonal changes, while the electrical configuration of the development would determine how much generation could be transferred directly to computing equipment.

At its full rated discharge power, the proposed battery has a nominal storage duration of two hours. Supplying a data centre for a longer period would depend on its electricity consumption, the battery’s available charge, conversion losses, and any capacity reserved for other purposes.

The original storage project’s grid balancing role also introduces a commercial consideration. Operating the battery to support the data centre could affect its availability for other electricity services, depending on the agreements governing its operation.

Coordinating those activities would require arrangements covering the allocation of generation, battery charging and discharging, and the import or export of electricity through the shared infrastructure. The developer has not published the proposed electrical topology or commercial terms governing those arrangements.

Planning and environmental requirements

Pathfinder’s experience developing renewable electricity projects provides a basis for coordinating the energy infrastructure with the proposed computing campus, but the separate planning approvals do not establish permission to build or operate the data centre.

The development would introduce additional requirements concerning building dimensions, construction traffic, mechanical equipment noise, electrical installations, and the environmental effects of continuous industrial activity.

Pace DC is also investigating opportunities to reuse heat generated by its computing equipment. The published proposals do not identify an external heat customer or establish the temperatures and quantities of thermal energy that could be recovered.

Establishing a heat recovery arrangement would require the developer to assess potential demand alongside the mechanical design of its computing facilities. The distance between the facility and prospective customers would influence the cost of distribution infrastructure, while the seasonal characteristics of demand would affect its utilisation.

The planning application should provide a more detailed basis for assessing these issues. In particular, the relationship between the proposed computing load and the adjacent generation and storage facilities will determine how much electricity the campus could obtain locally and how much it would need to import.

With the energy projects already consented, the next development milestone is the submission of the separate data centre planning application. The anticipated decision in summer 2027 will precede any construction timetable for the computing facilities.