Summary
- Applied Digital has completed base-build commissioning of the first 75MW phase at Polaris Forge 2 in North Dakota.
- The first 25MW data hall has achieved ready-for-service status following integrated customer fit-out.
- The building forms part of a 200MW long-term customer lease at the Harwood campus.
American data centre developer Applied Digital has completed commissioning of the base infrastructure supporting the first 75MW phase of its Polaris Forge 2 development in Harwood, North Dakota, with the initial 25MW data hall now available for customer service.
The company confirmed on 24 November that integrated fit-out of the first hall had been completed on schedule. The remaining two 25MW halls within the commissioned phase can now progress towards customer delivery.
The development forms part of a 150MW building leased in its entirety under a customer’s wider 200MW commitment at Polaris Forge 2. The company has not identified the hyperscale customer in its latest update.
Applied Digital commissions its 150MW buildings at the campus in two phases, each supporting three data halls with 25MW of critical IT capacity. Testing the underlying electrical and mechanical systems across those halls provides a commissioned infrastructure platform before individual customer fit-outs are completed.
The latest milestone follows similar phased delivery at Applied Digital’s Polaris Forge 1 campus in Ellendale. Completion of a further 75MW phase there on 1 October increased its operational critical IT capacity to 250MW across two buildings and ten data halls.
Applied Digital expects the initial Harwood facilities to contribute towards a combined 300MW of delivered capacity across its North Dakota developments by the end of 2026.
Shared infrastructure must be tested before customer delivery
The construction of individual data halls is closely connected to the delivery of the electrical and mechanical systems serving them. Although customers may occupy those halls separately, sections of the supporting facility infrastructure can be installed and commissioned together.
Electrical testing verifies that distribution equipment, protective devices, and power conversion systems operate within the parameters established during engineering design. It can also examine the behaviour of the installation during simulated failures or interruptions to normal electricity supplies.
Mechanical commissioning addresses the equipment responsible for maintaining appropriate environmental conditions, including cooling plant, pumps, pipework, and associated controls.
Integrated testing is particularly important where separate infrastructure systems are operationally dependent on one another. A power disturbance affecting mechanical equipment could compromise cooling even if the electrical supply to computing equipment remains uninterrupted.
Similarly, a control system failure may prevent otherwise functional mechanical or electrical equipment from responding correctly to changes in operating conditions.
Commissioning infrastructure supporting several halls together can establish whether shared systems behave as intended before individual customer installations are completed.
Further testing and acceptance remain necessary at hall level. The distinction between the 75MW commissioned phase and the initial 25MW service milestone reflects that additional delivery work.
Neither figure establishes that the corresponding quantity of server hardware has already been installed and is actively processing workloads.
Commercial commitments depend on physical delivery
Applied Digital’s infrastructure portfolio now incorporates more than $41bn of contracted base-term lease revenue, following a separate 150MW agreement reported by DataCentral on 24 November.
The scale of its commercial commitments places increasing importance on construction and commissioning performance. Contracted revenue represents the value of future services over the relevant lease periods, rather than money already received for completed developments.
Delivering individual halls in stages can reduce the interval between construction expenditure and customer occupation, subject to the acceptance and payment provisions of the corresponding contracts.
However, developers must coordinate continuing construction with infrastructure that has already entered service. Subsequent equipment installation, electrical isolation, and mechanical testing cannot be allowed to compromise the resilience of occupied facilities.
Those requirements become more complex where a campus includes multiple buildings progressing through construction, fit-out, and commissioning simultaneously.
European developers pursuing similar delivery models face additional scheduling constraints associated with electricity network reinforcement, equipment manufacturing lead times, and specialist engineering resources.
The delivery of a completed building without sufficient power or commissioned cooling capacity does not establish operational readiness. Equally, an available electricity connection cannot generate computing services until the supporting facility infrastructure and customer equipment are ready.
Applied Digital’s Harwood milestone provides a measurable distinction between those stages of development. The remaining 50MW within the initial commissioned phase must still progress through customer fit-out and acceptance, while the second 75MW phase of the building remains a separate delivery requirement.