Summary
- Drax's capital markets update provisionally values powered land at approximately $1m per MW across three potential development phases.
- The company has formally requested 1.2GW of electricity import capacity from the system operator.
- The proposed initial 100MW phase remains dependent on commercial agreements, regulatory approvals, and final investment decisions.
Drax Group has disclosed a provisional valuation of approximately $1m per MW for the powered land underpinning its proposed data centre development at Drax Power Station in North Yorkshire, while formally requesting additional electricity import capacity for the estate.
The valuation, disclosed in the company’s capital markets update on 23 November, applies across all three potential phases of its development partnership with Brookfield, Radiant, and Qai.
Drax also confirmed that Radiant has been discussing commercial arrangements and technical requirements with prospective tenants during 2026. Those discussions remain ongoing, with no definitive customer agreement announced.
The valuation provides additional financial detail following the establishment of the proposed partnership earlier this month. It relates specifically to the commercial contribution of the powered development land, rather than the construction cost or eventual value of operational computing facilities.
Brookfield previously estimated that investment across the full development programme, including computing hardware, could exceed £20bn. Approximately £2.5bn of potential investment relates to the initial phase.
Electricity import capacity under assessment
Drax’s North Yorkshire estate extends across more than 1,000 acres and has access to approximately 4GW of grid infrastructure, alongside 2.6GW of active dispatchable electricity generation.
The company’s latest update discloses that it has formally requested 1.2GW of electricity import capacity from the system operator as part of its examination of the site’s longer-term development options.
Existing grid access does not establish an equivalent entitlement to import electricity. The proposed computing development would introduce a substantial new demand requirement at a location whose transmission infrastructure was principally established around electricity generation.
The first phase would use electricity imported from the grid and is targeting up to 100MW of computing capacity, with commercial operation anticipated from the first quarter of 2028.
Radiant would lead customer engagement, design, and commercial development, while Drax would oversee land, electricity integration, and planning arrangements.
The partnership’s second phase envisages a further 500MW of capacity between 2028 and 2031, potentially supplied directly from Drax’s existing generation infrastructure through a long-term electricity purchase agreement.
A mechanism within the power station’s forthcoming biomass Contract for Difference allows Drax to request permission to allocate up to 500MW of generating capacity to a data centre during the agreement period. Approval would be subject to consideration by the government and the Low Carbon Contracts Company.
Any decision would need to account for electricity security, sustainability, and the financial interests of electricity consumers. Further expansion beyond 2031 would also depend on the commercial and regulatory arrangements established for supplying power directly to the development.
The existing biomass agreement runs from April 2027 to March 2031 and covers approximately 6TWh of annual generation. Drax estimates that this represents about 30% of the annual baseload output of its active generating units.
Wider energy investment programme
The potential data centre partnership forms part of Drax’s strategy to obtain additional commercial value from its existing generating estate while expanding its wider portfolio of electricity assets.
The company increased its managed generating capacity from 4GW in 2025 to 6.2GW in 2026. Existing investment commitments are expected to increase that figure to 7.6GW by 2029, with further opportunities potentially supporting a portfolio of approximately 9GW by 2031.
Drax is targeting adjusted earnings before interest, tax, depreciation, and amortisation of £800m–£900m in 2029, rising beyond £1bn by 2031.
Those financial ambitions encompass the company’s wider electricity business rather than establishing anticipated earnings from the data centre partnership.
Its development programme also includes an examination of whether two inactive units at Drax Power Station could provide electricity network stability services without generating electricity. Further work on that opportunity is expected during 2027.
Such services could help maintain the stability of the wider electricity system as the proportion of generation supplied by variable renewable sources increases. Their commercial development would represent a separate use of the estate’s existing infrastructure.
The proposed data centre partnership remains subject to planning permission, electricity network and regulatory approvals, acceptable customer commitments, definitive commercial agreements, and final investment decisions by the participating organisations.
Drax’s provisional land valuation therefore establishes one component of the proposed partnership’s commercial structure without confirming the amount of capacity that will ultimately be constructed.
Progress on the initial development will depend on the outcome of Radiant’s tenant discussions and the electricity arrangements required to deliver the proposed facility, while the larger import request forms part of Drax’s wider assessment of the estate’s future role.