Environmental assessment details Greek AWS campus

Environmental assessment details Greek AWS campus

Environmental documentation reveals the scale of Greece’s proposed AWS campus. PPC plans four buildings providing 240MW of computing capacity at Agios Dimitrios, supported by 300MW of incoming electricity.

Environmental assessment details Greek AWS campus
Summary
  • The proposed campus would comprise 20 data halls distributed across four buildings.
  • PPC expects to finalise arrangements for the initial 300MW electricity connection during the first quarter of 2027.
  • Cooling water availability and existing transmission infrastructure underpin the proposed redevelopment of the former lignite power station.

Greek electricity utility Public Power Corporation (PPC) plans to develop four data centre buildings with a combined IT capacity of 240MW at its former Agios Dimitrios lignite power station, according to details contained within the project’s environmental assessment documentation.

The development near Kozani in Western Macedonia would accommodate computing infrastructure for Amazon Web Services (AWS), with a maximum incoming electrical demand of 300MW.

Each building would contain five data halls, providing 12MW of computing capacity per hall. PPC is also examining the possibility of expanding the wider campus to an incoming electricity capacity of 1GW, subject to further development approvals and investment.

The environmental documentation addresses the infrastructure required to support the initial development, including its electrical connections, mechanical installations, and access to cooling water from the nearby Polyfytos reservoir.

PPC expects to receive the terms of its connection to the national electricity transmission system shortly, with the 300MW connection agreement anticipated during the first quarter of 2027.

The utility signed a binding memorandum of cooperation with AWS in September, establishing a framework for the development and a proposed 15-year commercial relationship. Definitive commercial arrangements are still being developed.

Industrial redevelopment follows lignite retirement

PPC’s selection of Agios Dimitrios reflects the wider restructuring of its electricity generation portfolio in Western Macedonia, where the retirement of lignite facilities has made substantial areas of industrial land and associated infrastructure available for redevelopment.

The region’s former generating stations were connected to electricity transmission infrastructure designed to transport large volumes of power into the national network. Establishing computing facilities at those locations would reverse their relationship with the electricity system, replacing generation exports with substantial demand.

Although existing transmission assets provide a potential advantage over undeveloped locations, the network must still be assessed against the operating conditions created by the new load. Changes to power flows, connection protection, and network stability may require modifications to existing installations.

The 60MW difference between the proposed campus’s incoming electrical capacity and its computing capacity accommodates the electricity required by supporting infrastructure, including cooling systems, electrical distribution equipment, pumps, and controls.

Those installations must operate alongside the servers, with their electricity consumption varying according to the computing load and prevailing environmental conditions. The project’s maximum capacity figures therefore do not establish its annual energy efficiency.

PPC’s wider investment programme includes renewable generation, battery storage, pumped hydroelectric storage, and other electricity infrastructure. The proposed AWS agreement also envisages electricity procurement through long-term renewable power purchase arrangements.

Such contracts can establish the commercial conditions under which electricity is purchased over an extended period. Maintaining continuity of supply to the data centre remains a separate engineering requirement, governed by the availability of electricity connections and appropriate redundancy within the facility.

Cooling requirements inform environmental assessment

The proposed campus’s cooling arrangements envisage the use of water from the Polyfytos reservoir. Water-based cooling is expected to meet between 60% and 90% of the cooling requirement, depending on ambient conditions.

Outdoor temperatures and humidity influence the performance of heat rejection systems, particularly where cooling equipment can make use of favourable environmental conditions to reduce mechanical refrigeration requirements.

At the scale proposed for Agios Dimitrios, the relationship between cooling performance and water consumption will have implications for both operating expenditure and environmental compliance. Annual consumption will depend on the final equipment configuration, computing utilisation, and the frequency with which individual cooling systems operate.

The environmental assessment provides a basis for examining those requirements alongside the region’s existing industrial water infrastructure.

Greece has also introduced a more extensive regulatory framework for data centre development, with new provisions approved by Parliament earlier this month. PPC’s renewable electricity portfolio and the development work already undertaken at Kozani will influence its ability to meet the applicable conditions.

The company’s broader redevelopment programme for Western Macedonia includes new electricity generation and storage assets, as well as infrastructure intended to maintain district heating services previously supported by lignite generation.

Preliminary construction activity at the data centre campus could begin during early 2027, although delivery remains dependent on the progression of environmental permitting, electricity connection arrangements, and definitive commercial agreements.

PPC’s environmental assessment establishes a more detailed engineering basis for the initial development. The anticipated conclusion of the 300MW electricity connection agreement next year will represent a further milestone towards delivering the proposed computing capacity.


Stay updated with the latest insights and trends in the data centre industry by subscribing to our newsletter.

← Back

Thank you for your response. ✨