Summary
- Google's subsidiary Tricolore Computing reportedly submitted a 1.2GW connection request for a potential development at Villedieu-sur-Indre.
- RTE has reportedly proposed electricity connection infrastructure costing €67 million and requiring seven to eight years to deliver.
- Google says no final investment decision has been made on either the reported second location or its proposed Ozans campus.
Google has confirmed that it is exploring longer-term land and electricity infrastructure opportunities in central France, following reports that subsidiary Tricolore Computing submitted a 1.2GW grid connection request for a potential data centre development at Villedieu-sur-Indre.
The location would provide an additional development opportunity within the Indre department, where Google is already undertaking public consultation concerning a proposed computing campus at Ozans, near Étrechet.
Investigations by Mediapart and Lighthouse Reports indicate that Tricolore Computing submitted the Villedieu-sur-Indre connection request in May 2026. Electricity transmission operator RTE reportedly identified a connection arrangement costing €67 million, with an estimated delivery period of seven to eight years.
Xavier Elbaz, mayor of Villedieu-sur-Indre, has indicated that discussions concerning the potential development have been suspended while Google concentrates on its Ozans proposals. The landowner has also reportedly expressed opposition to selling the property to the company.
Google subsequently clarified that it is undertaking exploratory infrastructure planning rather than actively developing multiple projects in parallel. The company has not made a final investment decision concerning either location.
The reported connection request consequently establishes a potential electricity infrastructure requirement, rather than a confirmed 1.2GW computing campus. Even if the proposed connection arrangements were to proceed, the facility would remain subject to land acquisition, planning, environmental assessment, financing, and construction decisions.
Ozans establishes initial infrastructure requirements
Google’s proposed development at Ozans provides a more detailed indication of the electricity infrastructure the company is examining in the region. The project is undergoing public consultation between 2 November 2026 and 10 January 2027 under the oversight of France’s National Commission for Public Debate.
As DataCentral previously reported, the initial development phase envisages a first building around 2030, supported by a 120MW electricity connection.
RTE’s project documentation proposes establishing a dedicated 225kV substation within the Ozans development area, using existing transmission infrastructure and underground electricity connections to serve the first data centre building.
A subsequent development phase would involve new 400kV infrastructure, including a substation connected to the existing Éguzon–Marmagne transmission line. The proposed arrangement incorporates approximately ten kilometres of additional overhead transmission infrastructure, with a connection rated at 300MW for subsequent buildings.
The separate infrastructure requirements illustrate how developers can establish initial computing capacity while pursuing longer-term arrangements for larger developments. Later phases may require connection routes and equipment that differ substantially from those supporting the first building.
Google is also examining electricity supply and infrastructure options with Engie, including renewable electricity procurement, battery storage, grid flexibility, and heat recovery. The companies’ memorandum of understanding concerns the potential Ozans development and remains subject to further commercial arrangements, as outlined in DataCentral’s earlier coverage.
Longer-term electricity allocation
The reported seven-to-eight-year timetable for the potential Villedieu-sur-Indre connection reflects the longer-term infrastructure planning associated with electricity demand of this scale. A 1.2GW connection could accommodate approximately 10.5TWh of annual electricity consumption if operated continuously at its maximum rating, although actual consumption would depend on the facility’s development and operating characteristics.
Grid connection capacity must also accommodate the electricity requirements of supporting infrastructure. Mechanical cooling, electrical conversion and distribution losses, controls, and other building systems consume power alongside the computing equipment itself.
Transmission planning must account for prospective demand before developers necessarily commit to construction. Substation development, transmission reinforcement, land access, environmental permitting, and equipment procurement can each require substantial lead times.
However, a network operator’s assessment of a possible connection does not establish that the associated computing infrastructure will proceed. Developers may explore several locations to understand their relative costs, electricity availability, and development risks before selecting a site.
Those considerations are particularly important where alternative proposals would draw on infrastructure within the same geographical region. Evaluating prospective connections involves understanding their cumulative effect on electricity flows and the reinforcement that may be required elsewhere in the network.
Google currently relies on third-party data centre infrastructure for its French operations rather than operating a self-built campus in the country. Its Ozans proposal would therefore represent a substantial change in its physical infrastructure presence, should it proceed.
Villedieu-sur-Indre remains a less developed proposition, with land availability and investment decisions unresolved. The ongoing Ozans consultation provides a more immediate opportunity for local authorities, electricity infrastructure planners, and residents to examine the company’s proposed development and its associated network requirements.