NordVire submits Imatra data centre building plans

NordVire submits Imatra data centre building plans

NordVire has submitted plans for its proposed Imatra data centre. Municipal authorities will examine the application for two computing buildings and dedicated electrical infrastructure, with a planning decision anticipated in…

NordVire submits Imatra data centre building plans
Summary
  • NordVire has submitted a building permit application for its Mionipuisto development in south-eastern Finland.
  • Earlier development proposals identified approximately 130MW of capacity across a 30-hectare site.
  • Representations concerning the building application must be submitted by 10 December.

Finnish infrastructure developer NordVire has submitted a building permit application for its proposed data centre development in Imatra, advancing plans for a facility with previously announced capacity of approximately 130MW in south-eastern Finland.

The application covers two data centre buildings, associated entrance facilities, and an electricity substation at Mionipuisto in the Korvenkanta area, where Imatra municipality has agreed to lease approximately 30 hectares of industrial land to the developer.

Municipal authorities will examine the application and seek opinions from relevant regulatory bodies. Representations concerning the proposals must be submitted in writing by 10 December.

Imatra's building control department anticipates that a decision concerning the development could be reached during the early part of 2027.

Earlier development proposals identified provision for businesses capable of using heat recovered from the computing facilities.

The current application represents a progression from initial land agreements towards detailed development permissions, although it does not establish a construction completion date or confirm the availability of the full proposed electricity capacity.

NordVire founder Petri Valkama has indicated that initial construction activity would involve site preparation, including vegetation removal and groundworks.

The land agreement requires the developer to apply for building permission within one year for a development covering at least 20% of the reserved area.

Electricity infrastructure and development phasing

A dedicated substation will provide the interface between the external electricity supply and the distribution systems supporting the data centre's computing and mechanical equipment.

Its specification must account for the electricity connection voltage, available capacity, electrical protection requirements, and the arrangements necessary to maintain reliable supply to individual buildings.

For a development incorporating multiple computing facilities, the electrical architecture may also need to accommodate phased energisation as individual construction packages are completed.

Such arrangements can allow infrastructure to enter service incrementally, reducing the interval between initial investment and the commencement of customer operations. However, their viability depends on the configuration and timing of external electricity supply arrangements.

Building permission for the proposed substation would not, by itself, establish that sufficient network capacity has been secured. Electricity connection agreements, network reinforcement, equipment installation, and commissioning remain separate requirements.

The site is close to Finland’s main road 6, providing access for construction deliveries. Its approximately 30 hectares encompass the proposed electrical and computing infrastructure alongside land identified for other industrial activities, so the full leased area should not be interpreted as the data centre building footprint. A phased approach would also need to preserve suitable routes for heavy electrical equipment and future connections to neighbouring heat users, without assuming that these customers have already been contracted.

Earlier this month, NordVire outlined five prospective Finnish developments representing more than 1GW of potential capacity.

Individual projects remain dependent on local development permissions and infrastructure arrangements, meaning their combined proposed capacity cannot be interpreted as computing infrastructure committed to enter operation.

Industrial use of recovered heat

The Imatra development plans also reserve land for businesses capable of utilising heat generated by the proposed data centre.

Locating prospective industrial heat users close to computing infrastructure could reduce the distances over which thermal energy must be transported, potentially improving the commercial viability of heat recovery arrangements.

The temperature and volume of available thermal energy depend on the equipment installed, its utilisation, and the configuration of the cooling infrastructure. Industrial users may require temperatures above those available directly from data centre cooling circuits, necessitating additional equipment and electricity consumption.

The operating requirements of prospective heat users also influence the appropriate design of the recovery infrastructure. Manufacturing processes requiring continuous thermal energy may need alternative heat supplies during maintenance or interruptions to computing operations.

Conversely, businesses operating intermittently may be unable to utilise all the thermal energy generated by continuously operating computing facilities.

Providing land for these activities during initial development creates opportunities to coordinate industrial and computing infrastructure, but no confirmed commercial heat supply agreements have been disclosed.

NordVire's proposed Imatra development therefore incorporates two distinct commercial opportunities: provision of computing infrastructure and potential utilisation of its thermal output.

Both remain dependent on the progression of planning, electricity supply, construction, and customer arrangements.

With public representations due in December and a decision anticipated early next year, the development remains at the permitting stage rather than entering confirmed construction.