Summary
- Northern Europe Energy Group is pursuing a phased data centre development at Riihimäenportti VI under a preliminary municipal land agreement.
- The 16-hectare site requires detailed zoning, environmental assessment, and electricity connection arrangements before construction can proceed.
- Detailed planning is expected to begin in 2027, with construction potentially starting in 2029–2030 and completion extending into the 2030s.
Northern Europe Energy Group is planning a data centre on approximately 16 hectares of land in Riihimäki, Finland, with the municipality preparing a detailed zoning process for a development seeking at least 80,000 square metres of building rights.
The proposed campus would occupy the Riihimäenportti VI area near the junction of Lahdentie and Hämeenlinnantie. The site is largely undeveloped woodland rather than an existing industrial facility suitable for immediate conversion.
Riihimäki disclosed the developer’s identity and further project details on 16 November. The city’s Vitality Committee had previously approved a preliminary agreement to sell or lease the land in September 2026.
That agreement provides a basis for planning and feasibility work, not a final construction commitment. The developer has yet to establish the scheme’s electricity requirements, building configuration, financing, or operational capacity.
The city expects detailed zoning work to begin in 2027, with its council potentially considering the completed plan in 2029. Northern Europe Energy Group is targeting construction from approximately 2029–2030, subject to permissions and infrastructure arrangements.
The development would proceed in phases and could not be completed before the 2030s under the current indicative programme.
Planning must establish the permitted development
The proposed property extends across approximately 160,000 square metres. Northern Europe Energy Group is seeking building rights covering at least half that land area, although the final permitted floor space remains subject to the zoning process.
Riihimäki’s existing master plan identifies the wider area for employment-related development. A detailed local plan is necessary to determine the specific permitted uses, building arrangements, access requirements, and environmental conditions applying to the proposed data centre.
The project has not secured a final building permit. The developer also expects that an environmental impact assessment will be required, although the competent authority must determine the applicable procedure.
Its assessment would cover issues including traffic, noise, water, stormwater, landscape effects, electricity infrastructure, and the consequences of construction on neighbouring land.
Municipal ecological surveys carried out in 2022 identified a rare threatened plant species within the wider development area. The city intends to exclude its habitat from construction, with the detailed layout taking account of that restriction.
Although the existing land-use framework allows employment-related activity, the project will need to demonstrate that its eventual design satisfies the relevant planning and environmental requirements.
The extent of land available for buildings may therefore change as access routes, environmental protection measures, drainage arrangements, and supporting infrastructure are established.
Local residents and other interested parties will have opportunities to comment during the planning process and any subsequent environmental assessment.
Electricity arrangements remain at feasibility stage
Northern Europe Energy Group has not disclosed the proposed campus’s IT capacity or the amount of electricity it will require.
The company is discussing connection options with Finnish transmission system operator Fingrid and the local electricity network company. No final connection arrangement or contracted capacity has been announced.
Electricity access will influence the scale and timing of individual construction phases. The developer has indicated that the size of each phase will depend on available grid capacity, permitting requirements, and customer demand.
That approach leaves the eventual computing capacity unresolved. The proposed 80,000 square metres of building rights cannot be converted into a reliable IT load without further information about the internal design, equipment density, cooling requirements, and supporting electrical systems.
Large computing facilities also require electricity for cooling, power conversion, and auxiliary equipment in addition to the servers and networking equipment occupying the data halls.
Network connections, substations, internal distribution equipment, and resilience arrangements would need to be designed around the eventual facility load before construction and commissioning could progress.
The developer intends to investigate electricity procurement options, including renewable or lower-emission sources, but has not identified a completed power purchase agreement or an established operating energy mix.
Cooling design and environmental studies remain preliminary
The company’s preferred cooling approach currently uses a closed liquid circuit, with heat transferred to the surrounding air or recovered for another application.
Recirculating coolant can limit the need for continuous replacement water within the primary cooling system. Actual water consumption will depend on the final heat rejection equipment and its operating conditions.
The design remains provisional, and Northern Europe Energy Group has not supplied a measured water consumption estimate or confirmed the equipment to be installed.
Heat recovery is also being considered. The developer intends to examine whether excess heat could supply local district heating or industrial users, potentially including businesses requiring low-temperature process heat.
Such arrangements would require sufficient local demand, suitable heat transfer infrastructure, and commercial agreements. No external heat customer or completed recovery system has been announced.
Noise assessments will examine the proposed cooling plant, electrical equipment, and standby systems. The selected equipment and building layout will determine the measures necessary to meet applicable limits.
The city anticipates employment and property tax benefits if the project proceeds. Northern Europe Energy Group estimates that the initial phase could create dozens of permanent jobs, but it has not confirmed a final employment figure or the staffing requirements of individual facilities.
Construction employment would depend on the completed building programme and the pace at which development phases are undertaken.
The September land agreement and November project disclosure establish the site and developer, while the technical and financial characteristics remain to be determined.
Detailed zoning from 2027 will provide the next opportunity to assess the proposed buildings, electricity arrangements, environmental effects, and supporting infrastructure. Construction cannot begin until the necessary assessments, permissions, and network agreements are in place.