TBC Cambois data centre requires full EIA

TBC Cambois data centre requires full EIA

Northumberland County Council has ruled that TBC Partners’ proposed Cambois data centre requires a full environmental impact assessment before planning can progress.

TBC Cambois data centre requires full EIA
Summary
  • TBC Partners first sought an EIA screening opinion for its Cambois data centre in August.
  • Northumberland County Council has now determined that a full EIA will be required.
  • The project sits beside other large proposed data centre developments in the emerging Northumberland cluster.

TBC Partners will have to prepare a full environmental impact assessment for its proposed data centre at Cambois after Northumberland County Council concluded that the development could create significant environmental effects.

The decision advances an early-stage planning process first reported by DataCentral in August, when TBC Partners sought a screening opinion for approximately 12 hectares of land at Factory Road.

The developer has indicated that the site could ultimately support as much as 300MW, although a full planning application has not yet been submitted and the eventual capacity remains subject to design, planning, power, and commercial development.

The EIA decision means the next application will need to assess environmental effects in considerably more detail rather than relying on the more limited information used for the initial screening request.

The assessment widens beyond the data centre boundary

Tetra Tech prepared the screening material on behalf of TBC Partners. Northumberland County Council has concluded that the scale and context of the proposed development warrant a full assessment.

That process is likely to examine subjects including landscape and visual effects, noise, ecology, traffic, air quality, construction impacts, drainage, energy infrastructure, and the cumulative effect of neighbouring development. The precise scope will be established through the planning process.

Cumulative assessment is particularly relevant at Cambois because the Factory Road proposal does not sit in isolation.

Immediately around the area are other large digital-infrastructure plans, including Wansbeck Regeneration’s West Sleekburn campus and QTS’s development around the former Blyth Power Station. The combined power, construction, landscape, and network effects can therefore differ materially from those of any single project considered alone.

TBC’s site is currently used for aggregates, timber, plant, machinery, and haulage activities and formed part of the former GlaxoSmithKline industrial estate. Layout options have included one or two principal data centre buildings and an on-site substation.

Environmental review arrives before final design

The screening process is deliberately early. Requiring an EIA does not amount to planning refusal, nor does it indicate that the development will ultimately be approved. It determines the level of environmental evidence that must accompany a future planning application.

That distinction is important for data centre projects because infrastructure design can change materially before submission. Power capacity, generator numbers, cooling equipment, building massing, construction phasing, drainage, and access arrangements all affect the environmental assessment.

Earlier TBC material indicated that the proposed campus could use closed-loop, air-cooled conditioning to limit water consumption and examine opportunities for waste-heat reuse. Those concepts will require greater technical definition as the EIA and planning design develop.

The project is also expected to need substantial electrical infrastructure. A capacity approaching the developer’s previously indicated 300MW ceiling would place electricity connection and substation delivery near the centre of the programme, although no final connection arrangement has been published.

Cambois is becoming one of the UK’s more concentrated proposed data centre development areas. That creates possible advantages in common power, fibre, construction expertise, and supply chain availability, but it also makes cumulative planning effects harder to separate.

A cluster of very large sites can place simultaneous pressure on grid infrastructure, roads, construction labour, environmental mitigation, and local planning resources. Those effects are precisely the type of issues that a full EIA can be required to examine.

TBC Partners now moves from asking whether a detailed assessment is necessary to preparing that assessment. The next meaningful milestone will be a full planning application setting out the final project envelope, electrical architecture, building design, mitigation measures, and construction programme.