Colorado campus proposes agricultural heat recovery

Colorado campus proposes agricultural heat recovery

A proposed Colorado development would combine computing infrastructure with agriculture. Ecoasis AgTech Park intends to use recovered data centre heat to support commercial greenhouse production near Pueblo, with a planning…

Colorado campus proposes agricultural heat recovery
Summary
  • The proposed 272-acre development would accommodate up to 160 acres of commercial greenhouses alongside computing infrastructure.
  • The developers intend to use recovered heat, although detailed electrical, thermal, and water requirements remain undisclosed.
  • A comparable Dutch initiative in Uithoorn is examining the integration of data centre heat with established commercial horticulture.

A proposed agricultural development in southern Colorado would integrate commercial greenhouse production with a data centre, using heat recovered from computing equipment to support food cultivation across a planned 272-acre site near Pueblo.

The Ecoasis AgTech Park development would accommodate up to 160 acres of commercial greenhouses alongside computing infrastructure, creating a combined industrial and agricultural development near Interstate 25 and Greenhorn Drive.

The developers presented the proposals to local residents on 16 November and expect to submit a planned unit development application to Pueblo County during December.

Their plans envisage the cultivation of crops including tomatoes, berries, and leafy vegetables, with the greenhouse infrastructure intended to support production throughout the year.

Recovering thermal energy from the data centre could reduce the agricultural operation’s requirement for separately generated heat. However, the developers have not disclosed the computing facility’s electrical capacity, recoverable thermal output, or proposed mechanical configuration.

The greenhouse development therefore establishes a potential market for recovered energy rather than demonstrating that the computing infrastructure could meet its heating requirements.

Matching heat production with agricultural demand

Computing equipment converts most of the electricity it consumes into heat, which must be removed continuously to maintain suitable operating temperatures.

Cooling infrastructure can provide a means of collecting that thermal energy before it is rejected into the surrounding environment. Where the design incorporates liquid cooling, coolant circuits and heat exchangers can transfer energy into separate distribution systems serving external users.

The temperature of the available heat depends on the equipment being cooled, its operating conditions, and the configuration of the mechanical installations.

Commercial greenhouses require controlled internal environments, with heating requirements influenced by crop selection, outdoor temperatures, humidity, ventilation, and the thermal performance of their structures.

Recovered data centre heat could potentially be supplied directly to greenhouse heating circuits or increased to the necessary temperature through heat pumps. The appropriate arrangement would depend on the temperatures and quantities of thermal energy available from the computing facility.

Locating the greenhouses alongside the data centre could reduce the distance over which recovered energy must be transported. Nevertheless, distributing heat across the proposed growing area would require substantial pipework, pumping equipment, and temperature controls.

The operators would also need to accommodate differences between the production and consumption of thermal energy.

Computing facilities can produce heat throughout the year, while greenhouse heating requirements vary with weather conditions and agricultural production schedules.

During warmer periods, the data centre may generate more heat than the agricultural operation can use. Independent heat rejection infrastructure would therefore remain necessary to maintain computing equipment temperatures.

Conversely, the agricultural operator would require alternative heating arrangements during interruptions to the computing facility or periods when its available thermal output falls below the greenhouse requirements.

The commercial viability of the arrangement depends partly on how those operational responsibilities, infrastructure costs, and continuity requirements are distributed between the two businesses.

Dutch horticulture provides a comparable development model

A partnership established in the Netherlands during July provides a European comparison for the proposed Colorado development.

Switch Datacenters and the municipality of Uithoorn signed an agreement with a collective of greenhouse growers in the De Kwakel-Kudelstaart area to progress a heating network supplied by a proposed data centre.

The initiative also involves Greenport Aalsmeer and electricity network operator Liander. Its objective is to establish infrastructure that allows commercial growers to replace some of their existing natural gas heating requirements with recovered thermal energy.

Unlike the Colorado proposal, the Dutch initiative involves established horticultural businesses seeking an alternative source of heat. Its development therefore requires coordination between existing agricultural infrastructure, a proposed computing facility, and the network distributing energy between them.

The involvement of the electricity network operator also illustrates the relationship between heat recovery and wider energy infrastructure. Heat pumps, circulation equipment, and computing installations all create electricity requirements that must be accommodated within the development’s overall energy arrangements.

Both projects remain dependent on establishing commercially and technically viable connections between the heat source and its prospective consumers.

Water availability introduces a further consideration for the Colorado development. Greenhouse irrigation and data centre cooling can create different water consumption requirements, depending on crop selection, mechanical systems, and operating conditions.

The developers have not published a verified combined water consumption assessment or detailed thermal balance for the proposed infrastructure.

The anticipated county planning application should provide additional information concerning those requirements, alongside electricity demand, construction arrangements, and environmental effects.

The project’s ability to supply useful heat to commercial greenhouses will ultimately depend on the compatibility of the computing and agricultural operations. Its proposed growing area alone cannot establish the quantity of recovered thermal energy that could be utilised.